| 10 - STACKING LCC44/84 UNITS ON CSUB610 IN THE PERPENDICULAR CONFIGURATION USING THE TOWER RIGGING SYSTEM
Figure 208. Mounting the rigging plate on CSUB610
in the perpendicular configuration
•
Insert the two (shorter) M6×45 mm screws into the two holes
in the rigging plate positioned nearest the right side of the
subwoofer, as seen from the front grille, and thread without
tightening them into the underlying threaded inserts in the
CSUB610.
•
Insert the four (longer) M6×50 mm screws into the four holes
in the rigging plate positioned nearer to the left side of the
enclosure, as seen from the front grille. Thread these without
tightening them into the underlying threaded inserts in the
CSUB610.
Figure 209. Top view of CSUB610 with Tower
Rigging System Plate installed in the perpendicular
configuration.
•
Using a 4 mm hex key (Allen type) with a length that allows
for sufficient leverage, tighten the screws into the inserts in
opposing pairs to firmly attach the rigging plate to the CSUB610.
the plate should be perfectly flush with the cabinet at every point
and there should be no movement possible.
Installing Outriggers on the CSUB610
Installing the subwoofer outriggers improves the stability of the CSUB610
or SUB310 when deployed vertically on the floor. The outriggers are
recommended in any application in which the subs are deployed in
public areas where people could bump into them or lean on them.
These are also REQUIRED in any application in which other loudspeaker
enclosures are coupled to the subwoofer in an upright position. The
CSUB610 unit can be deployed with LCC44, LCC84 or combinations of
these in either a parallel or perpendicular configuration. Each of these
configurations requires that the outriggers be installed in the appropriate
configuration.
WARNING
TIPPING HAZARD
Speaker enclosures stacked atop one another, even
when properly coupled, represent a tipping hazard.
TO
REDUCE
THE
RISK
OF
INJURY
OR
DAMAGE THAT COULD RESULT FROM POSSIBLE
TOPPLING OF LOUDSPEAKER ENCLOSURES,
THE INSTALLATION OF THE SUBWOOFER
OUTRIGGERS ON THE SUB310 AND CSUB610
IS REQUIRED WHENEVER ONE OR MORE
LOUDSPEAKER ENCLOSURES IS MOUNTED
ATOP ONE OF THESE UNITS, EITHER IN A
STACKED CONFIGURATION USING THE TOWER
RIGGING SYSTEM OR IN A SUB/SATELLITE
CONFIGURATION USING A SPEAKER POLE.
Installing Outriggers for perpendicular (omni) deployment
of CSUB610 with LCC44/84
If the application requires that the CSUB610 be oriented perpendicular to
the throw of the LCC44/84 units mounted atop it in order to save space,
the outriggers must be installed on the subwoofer in the perpendicular
configuration. This configuration is not recommended for applications
requiring the cardioid directivity of the CSUB610, as the directivity
axes of the subwoofer and the coupled LCC44/84 enclosures would be
perpendicular to each other. Therefore it should only be used with the
omnidirectional presets.
Figure 210. Raising the leveling feet of the
Outriggers.
•
Before installation, on each of the four Outriggers, raise the
leveling feet by screwing them in completely.