background image

CAUTION: 

The Baseline 10/100 Switch supports full 

duplex auto-negotiation. If the connected device does not 
support auto-negotiation, the Switch will operate in half 
duplex mode (even if the device is operating in full duplex 
mode). In such a configuration, you may notice some 
degradation of network performance. 3Com recommends 
that you use devices that are capable of auto-negotiation 
(and that you ensure that auto-negotiation is enabled, if 
it is a configurable option).

2

Activity/Link/Speed Status LEDs

The first (top) and third row of LEDs, which are colored yellow or 
green, show the activity and speed status of the related ports:

3

Duplex Status LEDs

The second and fourth (bottom) row of Status LEDs, which are 
colored yellow, show the duplex status of the related ports:

4

Power LED

The Power LED shows the power status of the Switch:

5

Self-adhesive Pads

The unit is supplied with four self-adhesive rubber pads.

You do not need to apply the pads if you intend to rack 
mount the unit.

If the unit is to be part of a free standing stack, apply the pads to 
each marked corner area on the underside of the unit. Place the 
unit on top of the lower unit, ensuring that the pads locate with 
the recesses of the lower unit.

Rear Panel Connections

6

Power Supply

The Baseline 10/100 Switch automatically adjusts to the supply 
voltage. Only use the power cord that is supplied with the 
Baseline 10/100 Switch.

Positioning the Baseline 10/100 Switch

CAUTION: 

If installing the Baseline 10/100 Switch in a 

stack of different size SuperStack 3 units, the smaller 
units must be installed above the larger ones. Do not 
have a free-standing stack of more than six units.

When deciding where to position the Baseline 10/100 Switch  
ensure that:

„

It is accessible and cables can be connected easily.

„

Cabling is away from sources of electrical noise such as 
radios, transmitters and broadband amplifiers, and away from 
power lines and fluorescent lighting fixtures.

„

The Switch is situated away from sources of electrically 
conductive dust, for example laser printers.

„

The AC supply used by the Switch is separate to those used 
by units that generate high levels of AC noise, for example air 
conditioning units and laser printers.

„

Water or moisture cannot enter the case of the unit.

„

Air flow around the unit and through the vents in the side of 
the case is not restricted (3Com recommends that you 
provide a minimum of 25 mm (1 in.) clearance).

To prolong the operational life of your units:

„

Never stack units more than six high if free-standing, and 
ensure that cables are supported so that they do not cause 
the stack to fall over.

„

Do not place objects on top of any unit or stack.

„

Do not obstruct any vents at the sides of the case.

Rack Mounting

The Baseline 10/100 Switch can be mounted in a 19-inch 
equipment rack using the Mounting Kit. Refer to “Mounting Kit 
Instructions” on page 5. 

Power Up

Use the following sequence to power up the Baseline 10/100 
Switch:

1

Check the network connections and cables.

2

Connect the power supply cable to the appropriate power 
socket on the rear panel of the unit; refer to 

6

 

Power 

Supply

.

3

Connect the plug to the power supply outlet socket and 
switch on the power supply at the socket.

When the switch is powered on, the Power LED should be lit on 
green. If it is not, refer to 

Power LED

.

Spot Checks

At frequent intervals you should visually check the Baseline 
10/100 Switch. Regular checks can give you an early warning of a 
possible failure; any problems can then be attended to when 
there will be least effect on users. Check that all external cabling 
connections are secure and that no cables are pulled taut.

If you experience any problems operating the Baseline 10/100 
Switch, refer to “Problem Solving” on page 5.

Status

Meaning

On

The link has been established.

Flashing

Packets are being received or transmitted on the port.

Off

If the link has not been established, either nothing is 
connected to the port, or there is a problem:

Check that the attached device is powered on.

Check that the cable is the correct type and is not faulty.

If these checks do not identify the cause of the problem, it 
may be that the unit or the device connected to the port is 
faulty. Contact your supplier for further advice.

Green

The link is operating at 100 Mbps.

Yellow

The link is operating at 10 Mbps.

!

Status

Meaning

On Yellow

The port is operating in full-duplex mode.

Off

The port is operating in half-duplex mode.

Status

Meaning

On Green

The unit is powered on and ready for use.

Off

The unit is not receiving power:

Check the power cord is connected correctly.

If the unit still does not operate, contact your supplier.

I

NSTALLING

 

THE

 S

WITCH

!

3

Summary of Contents for 3C16470

Page 1: ...be free standing or rack mounted in a wiring closet or equipment room The Baseline 10 100 Switch comes with One power cord for use with the Baseline 10 100 Switch Four self adhesive rubber pads One mo...

Page 2: ...tiating its speed and duplex mode half duplex or full duplex are automatically determined by the capabilities of the connected device Each port supports automatic MDI MDI X detection and can be connec...

Page 3: ...e cannot enter the case of the unit Air flow around the unit and through the vents in the side of the case is not restricted 3Com recommends that you provide a minimum of 25 mm 1 in clearance To prolo...

Page 4: ...oit tre agr dans le pays d utilisation Bitte unbedingt vor dem Einbauen des Baseline 10 100 Switch Einheit die folgenden Sicherheitsanweisungen durchlesen WARNUNG Die Installation und der Ausbau des G...

Page 5: ...ual activity There may be broadcast storms on the network Remove port connections one at a time waiting a few seconds between each port If the LEDs go off after removing a port connection the device t...

Page 6: ...nment Printing Office Washington DC 20402 Stock No 004 000 00345 4 In order to meet FCC emissions limits this equipment must be used only with cables which comply with IEEE 802 3 CE Statement Europe T...

Page 7: ...n to be environmentally friendly in all operations To uphold our policy we are committed to Establishing environmental performance standards that comply with national legislation and regulations Conse...

Page 8: ...ration frontpg pl Documentation Feedback Your suggestions are very important to us They will help make our documentation more useful to you Please e mail comments about this document to 3Com at pddtec...

Reviews: