Printer Advance Preparation Checklist

Unless governed by prior arrangement, 3D Systems is not responsible for loading the client software on

the user's workstation(s).  BEFORE THE PRINTER ARRIVES, ensure that your workstation is capable of

supporting the requirements of both the client software and communication with the machine via your

network. 
Review this list with a network administrator, IT department, facilities manager or other responsible

persons within your organization. Complete and place a check mark next to each item. Once

everything is complete, photocopy this page, and fax it to the number checked or provided on the

bottom of the inside back cover of this document. If no number is provided or relevant, then fax to +1

970-257-4601 (U.S.A). 
Please complete the following (if making a copy to fill in, please print): 
 
Company Name: _______________________________________________________________________ 
Contact (Print full name): ______________________________________________________________ 
Date faxed: ____________________________________________________________________________ 
Telephone (with area code): ___________________________________________________________ 
Email: __________________________________________________________________________________ 

 

Please place a check in each box once that item is complete.

Check
Box

Final installation site selected.  The intended physical location for each ProJet

®

 Professional Printing System(s) should be selected

in advance, and checked for adherence to the guidelines set out in this guide.

 

If required by the shipper, a method of removing the crate from the shipper’s truck has been arranged (forklift is required) and is
available to transfer the crate(s) to the de-crating location.

 

NETWORK CONNECTION IS INSTALLED. An RJ45 (UTP, female connection jack) Ethernet network connection for EACH printer that
is to be installed at the delivery site must be installed, tested and functioning.

 

Operating system and workstation configurations are compatible and meet the minimum requirements as stated in the section,
“Client Workstation Requirements”.

 

TCP/IP is installed and enabled.

 

Static IP address(es) has been allocated for each printer ordered. A permanent IP address on the network is assigned
(presumably by a Network Administrator) to each printer that is to be connected to the network. 
Enter IP address: ___________________________________________________

 

Test each IP address by pinging it, or by temporarily connecting a network resource (such as a workstation or a Printer) and
“pinging” from another workstation on the network.

 

Dedicated line, with a surge-and-spike-protected electrical power circuit for each printer, meeting one of the following
specifications.  Place check mark beside the appropriate specification:
____ 115 VAC, 50/60 Hz (dedicated 20 amp breaker)
____ 230 VAC 50/60 Hz (dedicated 15 amp breaker)

 

Optional uninterrupted power supply (customer purchased) with a

minimum 5kVA supplying 120V. The customer is responsible for correct power to the

UPS and from the UPS to operate the ProJet 5600 at correct voltages and current

requirements.  90-120VAC @ 20amps maximum. Place a check mark to either Yes or No

:

____ Yes

____ No

 

Before the printer is installed into this facility, we acknowledge that the installation site complies with

the specifications stated in the 

ProJet™ Facility Requirements Guide. Once the printer is installed, we agree not to alter any

Summary of Contents for ProJet MJP 5600

Page 1: ...m projetmjp5600 facility requirements guide for the most up to date Facility Requirements Guide About this manual This document includes all of the overall facility requirements that will be needed to have a successful installation when our 3D Systems Field Service Engineer or 3D Systems certified servicing reseller arrive to install your 3D printer ...

Page 2: ...A description of hardware software part material networking components and documentation that comprise the ProJet Professional Printing System An overview of the site requirements in typical engineering and design work spaces These involve basic access electrical and environmental conditions for configuring a safe and efficient work area A checklist is included to ensure that the facility is adequate...

Page 3: ...n or behind the access panel Avoid contact Hot surfaces can cause burn injury or fire Allow surface to cool before touching Access panels are for service only and should be opened only by certified service personnel or trained maintenance personnel HARMFUL IRRITANT WARNING Indicates that skin or eye irritation could result while exposed to a chemical composition CAUTION Indicates the possibility of ...

Page 4: ...terials VisiJet build material is for production of the actual prints and the VisiJet support material produces the required support structures necessary to build 3 dimensional prints These materials are formulated exclusively for use with the ProJet Professional Printing System What is Included with a ProJet Professional Printing System The printer ships with one crated ProJet Professional Printi...

Page 5: ...Dimensions Printer Weight and Dimensions Weight 935 kg 2060 lbs Dimensions H x W x D 162 x 170 x 90 cm 63 8 x 66 9 x 35 4 in Printer Weight and Dimensions Crated Weight 1180 Kg 2600 lbs Dimensions H x W x D 203 2 x 200 7 x 165 cm 80 x 79 x 65 in Space Planning Below is a suggested floor plan for the printer installation Each printer requires use of a dedicated circuit Multiple printers CAN NOT be l...

Page 6: ... accepts no responsibility for damaged defective or incomplete systems uncrated by anyone other than 3D Systems Field Service Engineer or authorized reseller CAUTION The casters provided have a small diameter and are not intended for use on rough or uneven surfaces including carpet CAUTION To avoid the risk of tipping the printer when moving between locations only push from the left or right end o...

Page 7: ...may be affected by an outside source e g lightning strikes power interruption etc A 5kVA UPS supplying 120V to the product is required The machine shall be powered by 100 120V nominal when a UPS is utilized Some examples of suppliers are Toshiba APC Eaton and Liebert For International 230V markets a stepdown transformer is always required Power loss during a build will cause the build to fail and c...

Page 8: ...eller at the time of installation and should also be known by personnel installing the client software They will need access either to the appropriate subnet mask or the individual IP address of each printer to complete the workstation software installation and to enable access to any printer on the network Not all networks have TCP IP installed Make sure to have a network administrator check that...

Page 9: ...t with local and other applicable laws and regulations governing such materials Refer to the VisiJet materials SDS sheets prior to shipment of the ProJet Professional Modeling System Discuss your organization s methods for disposing or recycling of such material with your facilities manager or for more information contact 3D Systems Customer Support Hot line here ...

Page 10: ...imits The operating temperature range should be between 18 28 C 64 82 F optimal operational environment is 21 24 C 70 75 F Humidity Humidity should be maintained at a minimum 30 and a maximum 70 relative humidity Optimal is 35 45 relative humidity Lighting The printer is equipped with its own internal light build chamber and back lit operating panel control with display Vibration and Shock The pri...

Page 11: ...ower the printer ____ Optional UPS customer purchased 5kVA minimum properly wired for input and output voltages to operate the machine at designated voltages ____ Storage for extra printer material containers and other consumables ____ At least one 1 networked graphics workstation or CAD CAM CAE terminal meeting the requirements described in Client Workstation Requirements Note Retain the shipping...

Page 12: ...rom the shipper s truck has been arranged forklift is required and is available to transfer the crate s to the de crating location NETWORK CONNECTION IS INSTALLED An RJ45 UTP female connection jack Ethernet network connection for EACH printer that is to be installed at the delivery site must be installed tested and functioning Operating system and workstation configurations are compatible and meet ...

Page 13: ... with 3D Systems Customer Service Representative If alteration are made without consulting 3D Systems it may void the system s warranty Customer Signature _________________________________________________________ Date _______________ ...

Page 14: ...ct damages arising from the use of this document however caused and on any theory of liability This limitation will apply even if 3D Systems or an authorized dealer or representative has been otherwise advised of the possibility of such damage This document in whole or in part may be changed or modified at any time at the sole discretion of 3D Systems without notice ...

Page 15: ...rom your 3 D digital data We are dedicated to developing a relationship that extends beyond the terms of the sale Please take the time to contact 3D Systems with questions comments or suggestions about your ProJet Professional Printing System or other products or services 3D Systems strives for higher quality better products and comprehensive services to benefit our customers ...

Page 16: ...problem occurred for example when you submitted a job during the beginning or the end of a print or after power off recovery etc Customer Support Hotline Please contact your Customer Support Hotline at one of the following numbers US and Canada 888 598 1438 UK and EMEA 44 1442 279883 International 1 803 326 3930 General ProJet MJP 5600 service procedures must be performed only by a 3D Systems certi...

Page 17: ......

Reviews: