Chapter 2. Primary CLI Syntax Reference
42
3ware 9000 Series Serial ATA Controller CLI Guide
The
show rebuild
command displays the current rebuild background task
schedule as illustrated below.
//localhost> /c1 show rebuild
Rebuild Schedule for Controller /c1
========================================================
Slot Day Hour Duration Status
--------------------------------------------------------
1 Mon 2:00pm 10 hr(s) disabled
2 Thu 7:00pm 18 hr(s) disabled
3 - - - disabled
4 - - - disabled
5 - - - disabled
6 Mon 1:00am 4 hr(s) disabled
7 Sun 12:00am 1 hr(s) disabled
A status of “disabled” indicates that the task schedule is disabled. In this case,
the controller will not use the defined schedule timeslots. If the rebuild
command is entered manually, rebuilding will start within 10 to 15 minutes. It
will begin automatically if a rebuild is needed and a proper spare drive is set
up.
If the rebuild schedule is enabled while a rebuild process is underway, the
rebuild will pause until a scheduled time slot.
Example:
If a unit is in the initialization state at noon on Wednesday and the rebuild
schedule shown above is in use (with schedules disabled), you would see the
following status using the show command:
//localhost>/c1 show
Unit UnitType Status %Cmpl Stripe Size(GB) Cache AVerify IgnECC
---------------------------------------------------------------------------
u0 RAID-5 INITIALIZING 0 64K 521.466 ON OFF OFF
Port Status Unit Size Blocks Serial
---------------------------------------------------------------
p0 NOT-PRESENT - - - -
p1 OK u0 76.33 GB 160086528 Y2NXL7FE
p2 NOT-PRESENT - - - -
p3 OK u0 76.33 GB 160086528 Y2NXLB9E
p4 NOT-PRESENT - - - -
p5 OK u0 76.33 GB 160086528 Y2NXQPZE
p6 NOT-PRESENT - - - -
p7 OK u0 76.33 GB 160086528 Y2NXM4VE
p8 OK u0 74.53 GB 156301488 3JV3WTSE
p9 OK u0 74.53 GB 156301488 3JV3WRHC
p10 OK u0 74.53 GB 156301488 3JV3WQLQ
p11 OK u0 74.53 GB 156301488 3JV3WQLZ