This section is an overview of the steps required to commission an Aprisa SR radio network in the field:
Phase 1: Pre-installation
1.
Confirm path planning.
Page 48
2.
Ensure that the site preparation is complete:
Power requirements
Tower requirements
Environmental considerations, for example, temperature control
Mounting space
Page 51
Phase 2: Installing the radios
1.
Mount the radio.
Page 54
2.
Connect earthing to the radio.
Page 53
3.
Confirm that the:
Antenna is mounted and visually aligned
Feeder cable is connected to the antenna
Feeder connections are tightened to recommended level
Tower earthing is complete
4.
Install lightning protection.
Page 53
5.
Connect the coaxial jumper cable between the lightning protection and the
radio antenna port.
Page 58
6.
Connect the power to the radio.
Page 59