88
depending on national and local code
requirements and the application of the final
user. This condensate can stain the roof and
it can cause rust in some cases on metal roofs.
It is the responsibility of the end user or
contractor to determine if the condensate will
damage the roofing material.
Below freezing ambient air temperatures
during the heating mode can freeze any
condensation made in the drain lines. Smaller
amounts of condensation may not cause any
issues but for larger amounts of condensate
and low ambient air temperatures (below
freezing for multiple consecutive days) the
internal and external drain lines for the unit
will need to be heat traced to prevent
freezing. Heat traced internal drain lines are
required and a factory provided standard
feature on the condensate drain with the high
turndown modulating gas option.
A condensate
neutralizer
vessel
and
connecting tubing can be added to the
equipment if required. For below freezing
ambient
temperature
applications
the
neutralizer, connecting tubing and drain lines
will
require heat tracing
to prevent
condensate freezing. These components are
the responsibility of the installer.
Leak Testing
All components of gas supply system,
including manual shut off valves and the
piping in the interior of the unit, shall be leak
tested with a soap solution before operating
the appliance and at least on an annual basis
thereafter.
All gas fired heat exchangers are completely
tested at the factory before shipment. This
will remove nearly all of the oils that have
been used in the manufacturing process.
However, trace amounts may remain. When
performing the initial startup at the jobsite,
people or any other living animals that may
be sensitive to the residual odors or gases,
shall NOT be present in the conditioned
space during the startup. In all cases,
including the initial factory firing and testing,
any of the gases will be under the acceptable
level of concentration for human occupancy.
Do not use open flame or other source
of ignition for leak testing. Fire or
explosion
could
result
causing
property damage, personal injury, or
death.
LEAK CHECK GAS PIPE
The gas pipe in the unit must be
checked for leaks before startup. Leak
checking is the responsibility of the
installing contractor. All connections
must be checked for leaks annually
after installation. Failure to leak check
could result in fire, explosion, or other
hazardous situations.
Some soaps used for leak detection
can be corrosive to certain metals.
Rinse piping thoroughly after leak test
has been completed.
CAUTION
DANGER
DANGER
Those sensitive to odors or gases
from trace amounts of residual oils
must NOT be present
in the
conditioned space during the startup
of a gas fired installation.
WARNING
Summary of Contents for RZ Series
Page 2: ......
Page 31: ...31 Figure 4 4 Point Lift RZ Series Air Cooled Condenser Unit ...
Page 90: ...90 Gas Heater Operating Instructions ...
Page 108: ...108 Maintenance Log E Coated Coil ...
Page 110: ...110 ...
Page 111: ......