7.4 Structure positioning and installation
To install the lift, set some supports under the post upper ends, remove the pallets and position the posts,
one at a time, according to the diagram. Use a lifting system having minimum 500kg capacity.
Operations to be executed for mounting and installation:
Once you have positioned the two posts, mark the position of their anchor holes on the floor at the
correct distance and in a way that they are perfectly aligned.
Use a bit of 20mm to drill 10 anchor holes at a depth of 100mm minimum. Clean both holes and floor
from dust.
Introduce the anchor bolts M20 by hammering slightly. Set the anchor bolts at the other post checking their
positioning and alignment. Then introduce them by hammering slightly.
Before tightening the bolts by nuts, check that the two posts are well leveled.
Tighten the nuts by torque wrench setting at 150 Nm. If the bolts idle, they must be replaced by
bigger ones.
Only after having performed the above mentioned. operations you can go on mounting and
connecting the hydraulic and electric circuits.
Levelling the posts by means of a spirit level allows a correct installation of the different parts as well as
correct connections.