Installation and commissioning guide
1ZSC000563-AAF EN, REV. 4, 2021-06-23
15
Procedure
1.
Make sure that the crane and the soft lifting slings are approved for the total weight of the transport
box and bushing. Refer to the weight in the packing list.
2.
Attach soft lifting slings (8).
3.
Make sure that the angle of the soft lifting sling is not more than 20°.
4.
Carefully lift the transport box.
5.
Set down the transport box on a flat surface.
End of instruction
3.4.2 Lifting the bushing out of the transport box
Overview
G006949
Procedure
1.
Make sure that the cranes is approved for lifting the weight of the bushing. Refer to the net weight on
the packing list.
2.
Open the transport box.
NOTE!
The cover is attached with screws.
Summary of Contents for 1ZSC902110-AAA
Page 12: ...12 Installation and commissioning guide 1ZSC000563 AAF EN REV 4 2021 06 23 ...
Page 18: ...18 Installation and commissioning guide 1ZSC000563 AAF EN REV 4 2021 06 23 ...
Page 78: ...78 Installation and commissioning guide 1ZSC000563 AAF EN REV 4 2021 06 23 ...
Page 82: ...82 Installation and commissioning guide 1ZSC000563 AAF EN REV 4 2021 06 23 ...