28
Installation and commissioning guide
1ZSC000563-AAF EN, REV. 4, 2021-06-23
Procedure
1.
Install the springs (15), the guiding sleeves (16),
the pressing ring (17), and the hex screws M10
(18) to the bottom end of the bushing.
G005016
Torque
40 Nm
2.
Put the winding cables through the end-shield.
G005024
3.
Install the winding cables to the bottom contact.
CAUTION!
Make sure that there is no tension in
the winding cables. Tension in the
winding cables will cause damage to
the draw rod or cables.
G005036
Torque
68 ±6 Nm
4.
Lift the bushing above the opening in the transformer.
Summary of Contents for 1ZSC902110-AAA
Page 12: ...12 Installation and commissioning guide 1ZSC000563 AAF EN REV 4 2021 06 23 ...
Page 18: ...18 Installation and commissioning guide 1ZSC000563 AAF EN REV 4 2021 06 23 ...
Page 78: ...78 Installation and commissioning guide 1ZSC000563 AAF EN REV 4 2021 06 23 ...
Page 82: ...82 Installation and commissioning guide 1ZSC000563 AAF EN REV 4 2021 06 23 ...