64
“Operation and installation manual”
EN
8. Operation and correct use
This chapter will give instruction on the correct use of the EVSE.
Chapter recipients:
• Owner
• Qualified installer
• User
8.1 Prepare for commissioning
Danger: Hazardous voltage
Do not commission the EVSE. Only a service engineer of the manufacturer is qualified to
commission the EVSE
1. Tell the owner that the EVSE is ready for commissioning
2. Make sure that the site is in accordance with these requirements:
• The EVSE is installed
• AC input power is available from the grid provider
• You are pre sent during the commissioning, for assistance and to energize the power to the EVSE on the
power distribution board
• Internet access is available, through cellular (default) or wired Ethernet connection.
In case of cellular connection, the signal strength must be greater than -85 dBm and should be measured
with a cellular network signal meter. Handheld mobile phones are not recommended for assessing signal
strength since they are not reliable measuring devices. Refer to
• An EV must be available with a compatible connection. If the EVSE has more than one connection type, an
EV of each type must be available
• Night illumination must be sufficient to easily see the charging cables and other obstacles around the EVSE
• The site operator or owner is available to receive instructions from the service engineer of the manufacturer
3. Make sure that these data are available:
• Contact data of the contact person on site
• Address of the EVSE
• Site name
• Exact location of the EVSE: longitude and latitude. If there are more EVSEs on one location, make sure that
the coordinates are slightly different (at least 0.0001 degree) so that the EVSEs are not at the same location
on the map.
• Specification of the external fuse at the power distribution board
• Date that the installation is done
• Special remarks, for example to decline the authorization for the service engineer of the manufacturer to
take photos
• Photo of the surroundings of the EVSE