Operation Manual / 4 Product description / A130-M.. - A145-M..
6 Periodic maintenance work / 6.2 Cleaning the compressor during
operation
© Copyright 2017 ABB. All rights reserved.
HZTL4031_EN
Revision F
August 2017
6.2.5
Carrying out wet cleaning of the compressor
Fig. 22: Carrying out wet cleaning of compressor
Engine load Filling amount of water pressure
vessel [dm
3
]
Water temperature
[°C]
Water injection
period [s]
50 … 85 %
0.4
5 … 30
10
Table 12: Parameters for wet cleaning of compressor
u
Remove sealing plug (27005).
u
Fill container with 0.4 dm
3
of pure water.
u
Screw in sealing plug (27005) again.
u
Push the valve activator (03) against the spring and hold for 10 … 15 seconds until the en-
tire volume of water is injected.
u
Continue to operate the engine for at least five minutes to ensure that all of the water is
flushed out of the system.
Not more than three cleaning cycles should be conducted consecutively. Before repeating
the process, continue to operate the engine for at least five minutes to ensure that all of the
water is flushed out of the system.