Do not install the drive on an elevated platform or a recess. The module
extraction/installation ramp included with the drive is only suitable for a height difference
of 50 mm (2 in) maximum (ie. the standard plinth height of the drive).
Necessary tools
The tools required for moving the unit to its final position, fastening it to the floor and
wall and tightening the connections are listed below:
•
crane, fork-lift or pallet truck (check load capacity!), slate/spud bar, jack and rollers
•
Pozidriv and Torx screwdrivers
•
torque wrench
•
set of wrenches or sockets.
Moving and unpacking the drive
Move the drive preferably in the original package to installation site as shown below to
avoid damaging the cabinet surfaces and door devices. When you use a pallet truck,
check its load capacity before you move the drive.
Horizontal package (frames R6…R9):
64 Mechanical installation
4
Summary of Contents for ACQ580-07
Page 1: ... ABB DRIVES FOR WATER ACQ580 07 Hardware manual ...
Page 2: ......
Page 4: ......
Page 8: ...4 Update notice ...
Page 20: ...16 ...
Page 26: ...Measuring points of frames R6 to R9 are shown below PE L1 L2 L3 22 Safety instructions ...
Page 32: ...28 ...
Page 38: ...34 ...
Page 66: ...62 ...
Page 69: ...Mechanical installation 65 ...
Page 73: ... Mechanical installation 69 ...
Page 75: ...Declaration of Conformity Mechanical installation 71 ...
Page 108: ...104 ...
Page 133: ...Electrical installation 129 ...
Page 142: ...138 ...
Page 156: ...152 ...
Page 162: ...158 ...
Page 171: ...Maintenance 167 ...
Page 177: ...3 4 Maintenance 173 ...
Page 184: ...14 13 15 16 17 Remove the flange 180 Maintenance ...
Page 187: ...3 4 5 6 Remove the mounting plate Maintenance 183 ...
Page 189: ...8 Disconnect the drive module output busbars M12 70 N m 52 lbf ft 7 8 Maintenance 185 ...
Page 193: ...4 5 3 6 Remove the mounting plate Maintenance 189 ...
Page 195: ...8 Disconnect the drive module output busbars M12 70 N m 52 lbf ft 7 8 Maintenance 191 ...
Page 218: ...Frame R6 Input and motor cable terminal dimensions option F289 DET A 214 Technical data ...
Page 233: ...Frame R9 Input and motor cable terminal dimensions option F289 Technical data 229 ...
Page 257: ...13 Dimension drawings Example dimension drawings are shown below Dimension drawings 253 ...
Page 258: ...Frames R6 and R7 IP21 UL Type 1 254 Dimension drawings ...
Page 259: ...Frames R6 and R7 B054 IP42 UL Type 1 Filtered Dimension drawings 255 ...
Page 260: ...Frames R6 and R7 B055 IP54 UL Type 12 256 Dimension drawings ...
Page 261: ...Frames R6 and R7 H351 and H353 top entry and exit Dimension drawings 257 ...
Page 262: ...Frames R6 and R7 F289 258 Dimension drawings ...
Page 263: ...Frames R6 and R7 F289 H351 H353 Dimension drawings 259 ...
Page 264: ...Frames R8 and R9 IP21 UL Type 1 260 Dimension drawings ...
Page 265: ...Frames R8 and R9 B054 IP42 UL Type 1 Filtered Dimension drawings 261 ...
Page 266: ...Frames R8 and R9 B055 IP54 UL Type 12 262 Dimension drawings ...
Page 267: ...Frames R8 and R9 H351 and H353 top entry and exit Dimension drawings 263 ...
Page 268: ...Frames R8 and R9 F289 264 Dimension drawings ...
Page 269: ...Frames R8 and R9 F289 H351 H353 Dimension drawings 265 ...
Page 295: ... Declaration of conformity The Safe torque off function 291 ...
Page 296: ...292 ...
Page 302: ...298 ...
Page 309: ...CMOD 01 multifunction extension module external 24 V AC DC and digital I O 305 ...
Page 310: ...306 ...
Page 316: ...312 CMOD 02 multifunction extension module external 24 V AC DC and isolated PTC interface ...
Page 322: ...318 ...