Installation checklist and start-up
Installation checklist and start-up
What this chapter contains
This chapter contains an installation checklist, a start-up procedure for the drive, and
listings of parameters specific to the ACQ800-37.
Installation checklist
Check the mechanical and electrical installation of the drive before start-up. Go
through the checklist below together with another person.
WARNING!
Only qualified electricians are allowed to commission the drive. Read
on the first pages of this manual. Neglecting the
safety instructions can cause injury or death.
Check…
MECHANICAL INSTALLATION
The ambient operating conditions are allowed. See
.
The unit is fixed properly to floor. See
The cooling air will flow freely.
ELECTRICAL INSTALLATION
Planning the electrical installation, Electrical installation.
The motor and the driven equipment are ready for start.
The drive is grounded properly.
The supply (input power) voltage matches the nominal input voltage of the drive.
The supply (input power) connection to the input terminals are OK and the phase order is correct.
Appropriate supply (input power) fuses and disconnector are installed.
The motor connections at the output terminals are OK.
The motor cable is routed away from other cables.
Settings of the auxiliary voltage transformer.
There are no power factor compensation capacitors in the motor cable.
The external control connections inside the drive are OK.
There are no tools, foreign objects or dust from drilling inside the drive.
Supply (input power) voltage cannot be applied to the output of the drive (with a bypass connection).
All shrouds are in place.
Summary of Contents for ACQ800 Series
Page 1: ...Hardware Manual ACQ800 37 Drives 55 to 450 kW 75 to 550 hp ACQ800 ...
Page 4: ......
Page 12: ...12 ACQ800 37 Hardware Manual Safety instructions ...
Page 24: ...24 ACQ800 37 Hardware Manual About this manual ...
Page 52: ...52 ACQ800 37 Hardware Manual Mechanical installation ...
Page 78: ...78 ACQ800 37 Hardware Manual Electrical installation ...
Page 84: ...84 ACQ800 37 Hardware Manual Motor control and I O board RMIO ...
Page 92: ...92 ACQ800 37 Hardware Manual Installation checklist and start up ...
Page 106: ...106 ACQ800 37 Hardware Manual Maintenance 3 4 5 6 8 7b 7a ...
Page 107: ...ACQ800 37 Hardware Manual 107 Maintenance 9 10 11 View from back ...
Page 123: ...ACQ800 37 Hardware Manual 123 Technical data Declaration of Conformity ...
Page 124: ...124 ACQ800 37 Hardware Manual Technical data ...
Page 128: ...128 ACQ800 37 Hardware Manual Dimensions Frame R6 ...
Page 129: ...ACQ800 37 Hardware Manual 129 Dimensions Frame R6 continued ...
Page 130: ...130 ACQ800 37 Hardware Manual Dimensions Frame R7i ...
Page 131: ...ACQ800 37 Hardware Manual 131 Dimensions Frame R7i continued ...
Page 132: ...132 ACQ800 37 Hardware Manual Dimensions Frame R7i continued ...
Page 133: ...ACQ800 37 Hardware Manual 133 Dimensions Frame R7i continued ...
Page 134: ...134 ACQ800 37 Hardware Manual Dimensions Frame R8i ...
Page 135: ...ACQ800 37 Hardware Manual 135 Dimensions Frame R8i continued ...
Page 136: ...136 ACQ800 37 Hardware Manual Dimensions Frame R8i continued ...
Page 137: ...ACQ800 37 Hardware Manual 137 Dimensions Frame R8i continued ...