86
ACQ800-37 Hardware Manual
Installation checklist and start-up
Start-up procedure
Action
Additional information
WARNING!
Ensure that the disconnector of the supply transformer is
locked to open position, i.e. no voltage is, or cannot be connected to
drive inadvertently. Check also by measuring that there is no voltage
connected.
Basic checks with no voltage connected
If the unit is equipped with an air circuit breaker, check the current trip
limits of the breaker (preset at the factory).
General rule
Ensure the selectivity condition is fulfilled i.e. the breaker trips at a lower
current than the protection device of the supplying network, and that the
limit is high enough not to cause unnecessary trips during the
intermediate DC circuit load peak at start.
Long-term current limit
As a rule of thumb, this should be set to the rated AC current of the drive.
Peak current limit
As a rule of thumb, this should be set to a value 3-4 times the rated AC
current of the drive.
Optional device. See the delivery-
specific circuit diagrams.
Check the settings of the relays and breakers/switches of the auxiliary
circuits.
Optional devices. See delivery
specific circuit diagrams.
Disconnect any unfinished or unchecked 230/115 V AC cables that lead
from the terminal blocks to the outside of the equipment.
Connecting voltage to input terminals and auxiliary circuit
WARNING!
When voltage is connected to the input terminals, voltage
may also be connected to the auxiliary circuits of the drive.
Make sure that it is safe to apply voltage. Ensure that:
• nobody is working on the unit or circuits that are wired from outside into
the cabinets
• cabinet doors are closed
• covers of motor terminal boxes are in place.
Close the main breaker of the supply transformer.
Close the auxiliary circuit On/Off switch (Q100) if present.
Starting the supply unit
Close the main switch/disconnector (Q1).
Units with emergency stop: Turn the Start switch on the cabinet door
from 0 into START position for 2 seconds, then release the switch and
leave it in position 1.
Checks with the supply unit running
Check the settings of the earth fault (ground fault) monitoring device (if
present).
See chapter
.
Summary of Contents for ACQ800 Series
Page 1: ...Hardware Manual ACQ800 37 Drives 55 to 450 kW 75 to 550 hp ACQ800 ...
Page 4: ......
Page 12: ...12 ACQ800 37 Hardware Manual Safety instructions ...
Page 24: ...24 ACQ800 37 Hardware Manual About this manual ...
Page 52: ...52 ACQ800 37 Hardware Manual Mechanical installation ...
Page 78: ...78 ACQ800 37 Hardware Manual Electrical installation ...
Page 84: ...84 ACQ800 37 Hardware Manual Motor control and I O board RMIO ...
Page 92: ...92 ACQ800 37 Hardware Manual Installation checklist and start up ...
Page 106: ...106 ACQ800 37 Hardware Manual Maintenance 3 4 5 6 8 7b 7a ...
Page 107: ...ACQ800 37 Hardware Manual 107 Maintenance 9 10 11 View from back ...
Page 123: ...ACQ800 37 Hardware Manual 123 Technical data Declaration of Conformity ...
Page 124: ...124 ACQ800 37 Hardware Manual Technical data ...
Page 128: ...128 ACQ800 37 Hardware Manual Dimensions Frame R6 ...
Page 129: ...ACQ800 37 Hardware Manual 129 Dimensions Frame R6 continued ...
Page 130: ...130 ACQ800 37 Hardware Manual Dimensions Frame R7i ...
Page 131: ...ACQ800 37 Hardware Manual 131 Dimensions Frame R7i continued ...
Page 132: ...132 ACQ800 37 Hardware Manual Dimensions Frame R7i continued ...
Page 133: ...ACQ800 37 Hardware Manual 133 Dimensions Frame R7i continued ...
Page 134: ...134 ACQ800 37 Hardware Manual Dimensions Frame R8i ...
Page 135: ...ACQ800 37 Hardware Manual 135 Dimensions Frame R8i continued ...
Page 136: ...136 ACQ800 37 Hardware Manual Dimensions Frame R8i continued ...
Page 137: ...ACQ800 37 Hardware Manual 137 Dimensions Frame R8i continued ...