5 Electrical installation
5.1 Insulation resistance test
5.2 Accessories resistance test
Network variation:
Space heater operation:
Space heater for slip ring unit:
Stator winding (1 min., 1000 VDC):
__________M
Ω
,
tested by________ kV, winding temperature:
______
º
C
Stator winding (15 / 60 s. or 1 / 10 min.):
PI =__________
,
tested by________ kV, winding temperature:
______
º
C
Rotor winding (1 min.):
__________M
Ω
,
tested by________ kV, winding temperature:
______
º
C
Exciter stator (1 min., 500 VDC):
__________M
Ω
,
tested by________ kV, winding temperature:
______
º
C
Space heater:
__________M
Ω
(500 VDC)
Temperature detectors:
__________M
Ω
(100 VDC)
N-end bearing insulation:
__________M
Ω
(100 VDC)
Stator 1 Pt 100:
Stator 2 Pt 100:
Stator 3 Pt 100:
Stator 4 Pt 100:
Stator 5 Pt 100:
Stator 6 Pt 100:
__________
Ω
__________
Ω
__________
Ω
__________
Ω
__________
Ω
__________
Ω
Bearing Pt 100 D-end:
Bearing Pt 100 N-end:
__________
Ω
__________
Ω
Air temperature 1 Pt 100:
Air temperature 2 Pt 100:
__________
Ω
__________
Ω
Anti-condensation heater:
__________
Ω
no
yes, voltage:______-______V, frequency:_____-______Hz
no
manual
automatic, controlled by:_________________
no
yes, voltage:_____________V, power:_______________W