background image

4

3

2

WARNING:  THE CiC ADAPTER COULD DROP DURING THIS OPERATION.  ATTACH APPROPRIATELY SIZED 

AND RATED LIFTING DEVICES WHICH EXCEED THE RATINGS LISTING IN TABLE B ON PAGE 1 
BEFORE PROCEEDING.

Ÿ

Lower the CiC adapter onto the rails from the 
lifting points as shown so that the rollers rest in 
the guide rails.

Fig. 3

Fig. 5

Ÿ

Place the Extended cradle rails 
(a)(fig. 3) onto Switchgear rails  
until the side levers drop down to
lock the switchgear rails 

Ÿ

Push the CiC adapter on the cradle rails into

 

the switchgear cell.

 

Open condition

Closed condition

Fig. 4

Summary of Contents for DB BREAKER

Page 1: ...then locked into the legacy DB switchgear thus making use of the of the Emax 2 plug in features as established in the operation and maintenance manual of the new Emax 2 circuit breaker without having...

Page 2: ...lifting must use appropriate safety equipment A 1 DB BREAKER Tools Required Drill Machine Rack out the breaker using the DB rack out leverage tool g 1 Remove the legacy OEM circuit breaker Open the d...

Page 3: ...3 onto Switchgear rails until the side levers drop down to lock the switchgear rails Lower the CiC adapter onto the rails as shown so that the rollers rest in the guide rails g 4 Fig 3 Fig 4 Push the...

Page 4: ...y lock the breaker with switchgear as shown in g 9 Remove all the tools and equipment used for the CiC adapter installation and clean o any processing residues and metal scraps Rack in the CiC adapter...

Page 5: ...stance is detected stop immediately and correct the situation before proceeding Pull out the CiC adapter from switchgear rails WARNING THE CiC ADAPTER COULD DROP DURING THIS OPERATION FASTEN IT TO A L...

Page 6: ...ge of handling and lifting must use appropriate safety equipment A 1 DB BREAKER Tools Required Rack out the breaker using the DB rack out leverage tool g 1 Remove the legacy OEM circuit breaker Open t...

Page 7: ...ABLE B ON PAGE 1 BEFORE PROCEEDING Lower the CiC adapter onto the rails from the lifting points as shown so that the rollers rest in the guide rails Fig 3 Fig 5 Place the Extended cradle rails a g 3 o...

Page 8: ...Examine what is causing the interference and correct the situation Remove all the tools and equipment used for the CiC adapter installation and clean o any processing residues and metal scraps Optiona...

Page 9: ...P DURING THIS OPERATION FASTEN IT TO A LIFTING TRUCK BEFORE PROCEEDING Pull out the CiC adapter from switchgear cell until they it is on extended rails as shown in g 12 Lift the CiC adapter from the r...

Page 10: ...www abb com Doc N 2TSA450001P1011 LK8 LKE8 LKD8 LK16 LKE16 TO EMAX 2 Senatobia MS 38668 Phone 1 662 562 0700 For more information please contact your local ABB Field Representative or Service Center...