Contactor Control Board
Figure 10
-
4: BJN Low Voltage Battery Disconnect (LVBD) Contactor Control Board
Battery and Alarm Fuses and Circuit Breakers
If the battery connection panel is equipped with battery fuses and alarm fuses,
do not
install them at
this time; the battery fuses should be installed after batteries have been connected.
If the battery connection panel is equipped with circuit breakers, they should be installed but left in
the OFF position.
Note:
The batteries will be connected in Section 13, Power Up and Installation Completion.