Installation and commissioning guide
2750 515-1 EN, REV. 14, 2020-06-26
21
3.
Remove the M10 bolts (6) and washers (7), and
then remove the outer terminal (5).
NOTE!
Keep the outer terminal (5), washers
(7) and bolts (6), they will be used
again.
G004690
4.
Install the lifting tool (1), the M10 bolts (6) and the
washers (7).
•
For GOE 250 to 950: align the side of the
lifting tool with the oil-level glasses (25).
•
For GOE 1050 to 2550: align the side of the
lifting tool with the oil-level guage (26).
NOTE!
The lifting tool is thinner than the outer
terminal, use stacks of washers or
shorter bolts to correctly install the
lifting tool.
G005056
Torque
40 ±4 Nm
5.
Attach soft lifting slings (8) from the lifting holes
through the lifting tool to the crane hook.
NOTE!
The diameter of the holes for the
lifting-slings in the lifting tool is Ø 50 or
Ø 28 mm.
G005015