Test tap
The bushing has a test tap that is connected to the outermost conductive layer of the condenser core. The test
tap is used to measure the bushing insulation by capacitance and dissipation factor. The cover connects the
outermost conductive layer to ground, and must always be installed when the bushing is energized.
The maximum one minute test voltage for this test tap is 2 kV
rms
. The test tap can be used as a power source,
if it is connected to an external capacitance. The operating voltage is limited to 600 V.
CAUTION!
Do not energize the bushing without a test adapter or the cover installed. The bushing is grounded
through the cover to prevent damage to the bushing.
G000388
1
Stud
2
Cover
3
Grounding spring
4
O-ring
Summary of Contents for GSBK 170
Page 46: ...46 Installation and maintenance guide 1ZSC000563 AAB EN REV 6 2019 09 12 ...
Page 52: ...52 Installation and maintenance guide 1ZSC000563 AAB EN REV 6 2019 09 12 ...
Page 54: ...54 Installation and maintenance guide 1ZSC000563 AAB EN REV 6 2019 09 12 ...
Page 62: ...62 Installation and maintenance guide 1ZSC000563 AAB EN REV 6 2019 09 12 ...
Page 66: ...66 Installation and maintenance guide 1ZSC000563 AAB EN REV 6 2019 09 12 ...
Page 70: ......
Page 71: ......