QUICK START GUIDE
Page 3
© 2021 ABB. All rights reserved.
Information –
Tools Required
a)
Cable Crimper
b)
Torque Wrench (0
-
240 in
-
lbs/28 Nm)
c)
Sockets –
Inch & Metric
d)
Wire cutters & Strippers
e)
Screw Drivers –
Flat & 2 Phillips
1.
Clearance: rear
-
3” (76
mm) to wall or surface min,
front
-
25"(635 mm) door swing, side
-
none.
2.
Place the Cabinet in position for installation.
3.
Mark anchor locations, move cabinet and drill anchor
holes.
4.
Relocate cabinet and install and torque floor anchors
per manufacturers specification.
1.External Cabinet: 2
-
hole ground lug landing
-
5/16”
on
1”
centers
(single hole mechanical lug option provided)
-
Minimum 6 AWG recommended.
The Integritas plant includes an internal copper ground bar that will be pre
-
wired to the ground connections of the
rectifier shelves, GFI
’
s and SPD
’
s. External grounding of the system should be made from this connection. Access
to the grounding bar is through the removeable rear or side panels. 2
-
hole ground lug landing
-
5/16”
on
1”
centers
(single hole mechanical lug option provided)
-
Minimum 6 AWG recommended. Ground Bar: ¼ x 20, on
5/8”
centers,
hardware provided
Step 1 –
Position and Secure the cabinet
Step 2
-
Ground the Cabinet