An extra O-ring is delivered together with the robot and must be fitted to the robot
during installation.
Note
Article number
Equipment
Used with protection class IP67,
and protection types Clean Room
and Foundry Plus.
3HAB3772-19
O-ring
Used to seal between the main
power cable and connector.
Robots with manipulator cables
routed from the rear of the base:
xx2000002338
Robots with manipulator cables
routed from below (3309-1):
xx2000002339
Customer cables - CP/CS cable
Article number
i
CP/CS cable length
3HAC067449-001
3 m
3HAC067449-002
7 m
3HAC067449-003
15 m
i
It is recommended to always use the CP/CS cable provided by ABB. If users still require to do
wiring by their own, make sure to use R1.C1 connector in M12 A-code 12p female type. It is the
responsibility of the users to guarantee the safety of the system when self-prepared cables and
connectors are used.
Customer cables - Ethernet floor cable
Article number
i
Ethernet floor cable length
3HAC067447-002
7 m
3HAC067447-003
15 m
i
It is recommended to always use the Ethernet floor cable provided by ABB. If users still require to
do wiring by their own, make sure to use R1.C2 connector in M12 X-code male type. It is the
responsibility of the users to guarantee the safety of the system when self-prepared cables and
connectors are used.
Product manual - IRB 1300
93
3HAC070390-001 Revision: G
© Copyright 2020-2022 ABB. All rights reserved.
3 Installation and commissioning
3.6.1 Robot cabling and connection points
Continued
Summary of Contents for IRB 1300
Page 1: ...ROBOTICS Product manual IRB 1300 ...
Page 8: ...This page is intentionally left blank ...
Page 36: ...This page is intentionally left blank ...
Page 100: ...This page is intentionally left blank ...
Page 746: ...This page is intentionally left blank ...
Page 762: ...This page is intentionally left blank ...
Page 764: ...This page is intentionally left blank ...
Page 768: ......
Page 769: ......