2.2 Unpacking
2.2.1 Pre-installation procedure
Introduction
This section is intended for use when unpacking and installing the robot for the
first time. It also contains information useful during later re-installation of the robot.
Prerequisites for installation personnel
Installation personnel working with an ABB product must:
•
be trained by ABB and have the required knowledge of mechanical and
electrical installation/maintenance/repair work
•
conform to all national and local codes.
Checking the pre-requisites for installation
Action
Make a visual inspection of the packaging and make sure that nothing is damaged.
1
Remove the packaging.
2
Check for any visible transport damage.
Note
Stop unpacking and contact ABB if transport damages are found.
3
Clean the unit with a lint-free cloth, if necessary.
4
Make sure that the lifting accessory used (if required) is suitable to handle the weight
of the robot as specified in:
5
If the robot is not installed directly, it must be stored as described in:
6
Make sure that the expected operating environment of the robot conforms to the
specifications as described in:
Operating conditions, robot on page 51
7
Before taking the robot to its installation site, make sure that the site conforms to:
•
Loads on foundation, robot on page 49
•
Protection classes, robot on page 51
•
Requirements, foundation on page 50
8
Before moving the robot, please observe the stability of the robot:
9
When these prerequisites are met, the robot can be taken to its installation site as
described in section:
On-site installation on page 67
10
Install required equipment, if any.
•
Signal lamp (option) on page 102
11
Continues on next page
48
Product manual - IRB 6700
3HAC044266-001 Revision: N
© Copyright 2013 - 2018 ABB. All rights reserved.
2 Installation and commissioning
2.2.1 Pre-installation procedure
Summary of Contents for IRB 6700 Series
Page 1: ...ROBOTICS Product manual IRB 6700 ...
Page 46: ...This page is intentionally left blank ...
Page 110: ...This page is intentionally left blank ...
Page 786: ...This page is intentionally left blank ...