2 Installation and commissioning
2.1 Before starting the track motion
Do this before starting the track motion
The following steps should be carried out before starting the track motion IRBT
2005.
Reference
Action
Compare the delivery checklist to the
identification plates and verify for accept-
ance according to
and
Unpack the track.
1
On-site installation on page 78
Read through and follow the information
and instructions for on-site installation of
the track.
2
Correct the track motion according to
Geometric alignment of track motion IRBT
2005 on page 96
.
Align and level the track.
3
Assembling the manipulator and cable tray
on page 108
Assemble the cable tray and manipulator
(for robot track).
4
Electrical installation on page 118
Install the cable chain and connect all
cables.
5
Inspection of cables and covers prior to
start-up on page 122
Verify covers and cable chain.
6
Electrical installation on page 118
Connect voltage to the system.
7
Starting the system for the first time on
page 123
Start up the system.
8
Creating and downloading a system on
page 124
Load software to the system.
9
Update revolution counters on page 265
Update the revolution counters.
10
Product manual - IRBT 2005
45
3HAC051130-001 Revision: F
© Copyright 2015 - 2018 ABB. All rights reserved.
2 Installation and commissioning
2.1 Before starting the track motion
Summary of Contents for IRBT 2005
Page 1: ...ROBOTICS Product manual IRBT 2005 ...
Page 8: ...This page is intentionally left blank ...
Page 44: ...This page is intentionally left blank ...
Page 148: ...This page is intentionally left blank ...
Page 284: ...This page is intentionally left blank ...
Page 286: ...This page is intentionally left blank ...
Page 289: ......