3.2 Overview of installation and commissioning procedure
Installation and commissioning steps
Carry out the following steps after delivery, to install and commission the track
motion IRT 710.
Reference
Action
Compare the delivery check to the identific-
ation plate and verify for acceptance accord-
ing to
Acceptance inspection on page 89
Unpack the track motion.
1
Installation and commissioning on page 85
Read through and follow the information
and instructions for on-site installation of
the track motion.
2
Lifting track motion using lifting slings
.
Lift the track motion.
3
Assembling the track motion IRT 710 on
page 120
Assemble the track motion.
4
Assembling the pedestal (option) on
page 139
Assembling the pedestal (option).
5
Assembly of the manipulator on page 141
Assemble the manipulator.
6
Electrical installation on page 143
.
Electrical installation.
7
Software installation on page 172
Software installation.
8
Updating revolution counters on page 342
Update the revolution counters.
9
86
Product manual - IRT 710
3HKA00000186299-001 Revision: B
© Copyright 2023 ABB. All rights reserved.
3 Installation and commissioning
3.2 Overview of installation and commissioning procedure
Summary of Contents for IRT 710
Page 1: ...ROBOTICS Product manual IRT 710 ...
Page 14: ...This page is intentionally left blank ...
Page 58: ...This page is intentionally left blank ...
Page 84: ...This page is intentionally left blank ...
Page 360: ...This page is intentionally left blank ...
Page 364: ...This page is intentionally left blank ...
Page 378: ...This page is intentionally left blank ...
Page 380: ...This page is intentionally left blank ...
Page 383: ......