background image

IB 6.2.11.1-2C 

Page 16 

ABB 

 

Shunt Trip Device (See Figure 8).

   

 

a. Turn trip rod (2, Figure 8) down until circuit breaker 
does not trip with plunger (3) held down.  
 
b. Close circuit breaker. 
 
c. Push plunger (3) down as far as possible and hold in 
this position while turning up trip rod (2) until circuit 
breaker just trips.  
 
d. Turn rod (2) up approximately 2½ to 3 turns. 

FIELD TESTING THE MPSC-2000 SOLID 
STATE TRIP SYSTEM

 

 
There are two ways to evaluate the MPSC-2000 solid 
state trip system: primary current injection through the 
breaker main contacts; and secondary current injection 
directly into the trip device.  Either method will test the 
trip device;  primary injection has the advantage of 
testing the current sensors and magnetic latch also.  
The following is a procedure for performing this field 
testing. 
 
Notes:  
 
1. Refer to time current curves TD-9651, TD-9652, and 
TD-9653. 
 
2. When checking calibration, disable the functions not 
being tested, or set them at their highest threshold and 
delay values.  

It is especially important to disable 

the Ground function when testing the other 
elements to prevent false tripping. 

 

5. Reference bulletin IB 6.1.2.8-1A for instructions on 
setting the MPSC-2000. 
 
6. These procedures are written for primary injection.  If 
the trip device is being tested by secondary current 
injection, contact ABB for special instructions and/or 
test equipment. 
 
7. The term “Range Selection” is used herein for 
consistency with previous MPS-type devices, and 
refers to the value of the “Rating” setting of the device.  
Like the previous MPS-type devices, the MPSC-2000 is 
capable of operating at two basic ratings:  one equal to 
the maximum frame continuous current rating of the 
breaker-mounted current sensors, and one equal to 
half the frame rating.  For example, on an 4000A 
breaker with 4000A sensors, the MPSC-2000 rating 
can be set to 4000A or 2000A.  When the rating is 
changed, other available settings are scaled 
accordingly;  thus the term “Range Selection”. 
 

Instantaneous or Short Time Threshold Test 

 
1. Either disable the trip elements not being tested, or 
set them to their highest threshold value.  Set the Long 
Time Delay to its maximum setting.  Set the Short Time 
delay to its minimum setting for Short Time tests. 
 
2. It is recommended that the Range Selection be set 
to its lowest value to minimize the current required for 
this test;  however, it may be set to either available 
value. 
 
3. Set the threshold and delay of the trip element being 
tested (again, it is recommended that a low value be 
used). 
 
4. Test for the actual threshold by increasing test 
current until the breaker trips.  It is important to 
increase the current fast enough so that the breaker will 
not be tripped by the Long Time element prior to 
completion of the test. 
 
5. The threshold tolerance is +/- 10% on all selector 

Table 4 - MPSC-2000 Typical Delay Bands

Delay Times (sec.)

Trip Element

Min.

Int.

Max

Long Time

8-13

20-33

61-100

Short Time (DEF)

0.080-0.170

0.200-0.320

0.350-0.500

Short Time (IIT)

0.160-0.250

0.520-0.780

0.910-1.350

Ground Trip (IIT)

0.05-0.17

0.20-0.32

0.35-0.50

3. The circuit breaker 
must be closed before 
each test below. 
 
4. Following each test, 
check the MPSC-2000 
event register to ensure 
that the correct element 
tripped the breaker, 
especially if test results 
appear to be incorrect. 
 

WARNING   WARNING   WARNING   WARNING 

RISK TO PERSONNEL AND FIRE CAN RESULT IF 
THE CIRCUIT BREAKER IS ENERGIZED WITHOUT 
THE HARNESS PLUG AND SCREWS IN PLACE. 

Summary of Contents for K-Line Plus KP-32

Page 1: ...IB 6 2 11 1 2C Installation Maintenance Instructions Low Voltage Power Circuit Breaker K Line Plus Types KP 32 KPE 32 KP 40 and KPE 40 ABB ...

Page 2: ...CE FOR EO BREAKERS 10 CLOSING SPRING OPERATION 11 INSTALLATION INITIAL TESTING REMOVAL 11 Installation 11 Checking Breaker Operation in TEST 11 Checking Breaker Operation in CONNECTED 11 Manual Closing Operation 12 Circuit Breaker Removal 12 MAINTENANCE AND ADJUSTMENTS 12 Periodic Maintenance Inspection 12 Arc Chutes 12 Insulation Structure 13 MPSC 2000 Trip Device Removal Installation 13 Electric...

Page 3: ...inal carton covering with waterproof paper and sealing to prevent infiltration of dirt Where conditions of high humidity prevail the use of heaters is recommended BASIC HANDLING Once the circuit breaker has been unbolted and removed from its shipping carton it should be turned to the upright position and placed on a flat surface to avoid damage to breaker parts For safety all handling in this posi...

Page 4: ...ip indicator is pushed in the circuit breaker mechanism can then be operated to close the circuit breaker contacts Padlocking Device Figure 1 Item 13 All K Line Plus circuit breakers are equipped with means of padlocking the circuit breaker mechanism in a trip tree position This is accomplished by the use of a locking plate to maintain the manual trip button in a tripping direction when the lockin...

Page 5: ...ional 10 Manual Trip Button 11 Drawout Lever 12 Manual Close Lever 13 Padlock Hasp 14 Motor Disconnect Switch EO only 15 Automatic Trip Indicator 16 Manual Charging Handle Optional 17 Position Indicator Label 18 Spring Charging Motor EO only 19 Racking Cam Rollers 20 Electrical Trip Close Buttons Optional Not Shown Figure 1 Typical Electrically Operated K Line Plus Circuit Breaker 1 19 3 4 5 18 17...

Page 6: ... 4 3 TC 1 51 2 a AS Trip Control Device 5 P18 A5 P4 P20 P8 2 P6 A2 P2 P19 P22 P1 P10 Solid State 3A 1 3 A3 P17 4 Trip A4 2 P5 4A 1 7 P9 P3 80 19 17 15 A14 A18 A16 23 21 A22 A20 14 18 16 20 22 A15 A21 A19 A17 A23 5 6 AS a 10 AS 9 a 12 AS 11 b 14 AS 13 a 16 AS 15 b 53 65 CSCS CSCS 64 63 56 57 NO C C NO B21 32 31 B22 B13 B9 B11 B7 34 32 36 B15 B17 B19 38 40 42 44 19 17 18 a AS 20 21 23 b AS 22 AS a 2...

Page 7: ...5 Not Used supplied with the breaker for pin out assignments 6 The assignments for pins B3 B6 will differ depending on whether the DESP option has been supplied See the MPSC 2000 schematic supplied with the breaker Notes 1 These assignments are provided for reference only and may be changed due to special requirements Some pins or plugs may not be present on all breaker configurations See the brea...

Page 8: ...ical closing functions of the breaker The anti pump feature of the SSCD prevents a second electrical closing until the first closing signal is released For example if the breaker is closed electrically and the signal is maintained the SSCD will not permit the breaker to be closed electrically again after a trip until the electrical close signal is released Shunt Trip The shunt trip is standard on ...

Page 9: ...the tripping energy from the primary current passing through the circuit breaker without the need for any additional power supply An external 9V battery is supplied to permit the user to access the MPSC 2000 s menus The battery is not required for correct operation of the trip device The battery will last only about 1 2 hours of actual use so the switch to this battery should be left in the off po...

Page 10: ...npacked from the factory may have the target displayed as a result of the factory testing performed on the breaker prior to shipping This target will reset when the circuit breaker is closed and sufficient primary current is flowing Continuous monitoring of the microprocessor function is programmed into the MPSC 2000 Watchdog circuits guard against the possibility of microprocessor disfunction due...

Page 11: ...See Figure 1 The circuit breaker must be in the OPEN position the racking crank 8 Figure 1 when inserted in opening is rotated counterclockwise until the racking cam roller 19 is rotated down into a 45 angle and the motor disconnect switch 14 for electrically operated circuit breakers is in the OFF position NOTE Lever 11 must be pushed down to permit the rotation of crank 8 Open compartment door a...

Page 12: ...nd close door MAINTENANCE AND ADJUSTMENTS SAFETY NOTES When it is necessary that the charging springs be charged or the circuit breaker be closed make sure to stay clear of operating parts Breakers shouId be withdrawn to TEST position for checking the breaker operation For further inspection adjustments cleaning or replacement of parts the circuit breaker should be withdrawn from the cell and move...

Page 13: ...dition the breaker will not be able to provide circuit protection NOTE Metallic screws must not be used to retain the trip system harness Should a metallic screw fall into the trip system serious damage can result Electrical Components EO Breakers Only 1 Rack the circuit breaker to the TEST position Make sure the closing springs are charged 2 Operate the local if installed or remote electrical clo...

Page 14: ...mp charging handle until the circuit breaker closing springs are heard to snap into the charged position also check the indicator 6 c Remove screw shift the shutter to the left and insert the spring retainer bracket so that its tips fit into the closing springs and its flanges fit into the holes in the closing spring guides NOTE Shutter cannot be opened unless breaker drawout mechanism is in the D...

Page 15: ...s the primary latch roller from moving to the left and opening the breaker If none of the various trip devices are acting on the tripper bar or the auxiliary latch tripper to open the breaker or to prevent the breaker from closing and the breaker still will not close then the following adjustment should be made a Turn screw 1 Figure 5 down to insure that the secondary trip latch will hold the seco...

Page 16: ...s one equal to the maximum frame continuous current rating of the breaker mounted current sensors and one equal to half the frame rating For example on an 4000A breaker with 4000A sensors the MPSC 2000 rating can be set to 4000A or 2000A When the rating is changed other available settings are scaled accordingly thus the term Range Selection Instantaneous or Short Time Threshold Test 1 Either disab...

Page 17: ...ly from twice to four times the Range Selection and that the trip curve is fixed and does not vary with pickup settings 7 Set test current so that it represents 1 5 times the ST Pickup setting Delays should be as shown in Table 4 Ground Trip Delay Tests Ground Trip Delay tests are performed by injecting current through a single phase of the breaker which appears to be a ground fault to the trip de...

Page 18: ...insulation to withstand overvoltages 2 A 60 cps alternating sinusoidal voltage rms value equal to the specific voltage shall be used All voltages used in the dielectric withstand test shall be measured in accordance with ANSI Measurement of Voltage in Dielectric Tests C68 1 3 Duration Of Test The dielectric test voltage shall be applied for a period of 60 seconds The duration of the test may be on...

Page 19: ...a short circuit ii Motors that have been in service may fail dielectric due to a normal accumulation of debris from the commutator Cleaning the motor will restore dielectric integrity iii Do not perform dielectric testing on the solid state trip system RENEWAL PARTS ABB recommends only those renewal parts be stocked that will be required to insure proper and timely maintenance of the breaker ...

Page 20: ...IB 6 2 11 1 2C Page 20 ABB NOTES ...

Page 21: ...IB 6 2 11 1 2C Page 21 ABB NOTES ...

Page 22: ...IB 6 2 11 1 2C Page 22 ABB ABB Inc P O Box 100524 Florence South Carolina 29501 Phone 843 413 4700 Fax 843 413 4850 ABB ...

Reviews: