Extend the switchgear cradle rails (a)(fig. 2) out
from the cell until the side levers (b) drop down to
hold the stop (c) on the rail.
Fig. 2
KP-800 (fig. 4), KP-1600 (fig. 5), and KP-2000
•
Lower the CiC on to the rails. The studs (e) on both sides
of the CiC should line up with and drop into the cutouts (f)
in the rails on each side of the CiC.
•
Rotate the cam lever (g) on both sides into the position as
shown.
The CiC cannot be installed in the gear with the
Emax 2 breaker installed.
•
Unscrew the breaker lock out pin (d)(fig. 3) on
both sides where shown until it stops and the
cam levers are free to rotate. Do not force them
past the stop or remove them.
Fig. 3
Fig. 4
Fig. 5
d
WARNING: THE CiC COULD DROP DURING THIS OPERATION. BEFORE PROCEEDING ATTACH
APPROPRIATELY SIZED AND RATED LIFTING DEVICE.
b
a
c
(both sides)
e
f
Lifting Points
e
f
g
g
1A