Operation Manual / Power2 650-M / Low-pressure stage
7 Periodic maintenance / 7.1 Foreword to maintenance
© Copyright 2022 ABB. All rights reserved.
HZTL4065_EN
Rev.E
March 2022
7
Periodic maintenance
7.1
Foreword to maintenance
Maintenance work includes regular visual controls and cleaning operations which are inten-
ded to ensure the trouble-free functioning of the low-pressure and high-pressure stage.
In this process, the exterior condition and the degree of contamination of the components
on which maintenance work is to be performed are determined.
Component to be main-
tained
Recommended cleaning interval
1)
Operating state
LP compressor
3)
25 … 100 h
Engine load: 50 … 100 %
HP compressor
3)
LP filter silencer
2)
500 h
Engine stopped
Table 15: Maintenance intervals
1) If the recommended cleaning intervals are incompatible with operation of the engine, con-
tact Turbo Systems.
2) If present
3) If compressor cleaning present
Compressor cleaning (if present)
We recommend cleaning the HP compressor after the LP compressor.
On V-engines with several low-pressure and/or high-pressure stages per engine, Turbo Sys-
tems recommends the parallel cleaning of the LP compressors as well as the parallel clean-
ing of the HP compressors.
This cleaning process is faster and reduces the risk of surging of the low-pressure and high-
pressure stages.
Page
50
/
119