34
A N N E X
Before starting the system
OK/ NOK
Execute the commissioning procedures specified by the batteries manufacturer
Start the system
(a)
While the system is running
(b)
Set the '
P setpoin
t' to -5 kW. It will charge the batteries at -5kW
Check the current of the inverter
Check the power absorbed by the inverter
Check the batteries voltage through the BMS
Check the batteries current through the BMS
Set the '
P setpoint
' to 0
Check the current of the inverter. Shall be 0
Set the '
P setpoint
' to 5kW.It will discharge the batteries at -5kW
Check the current of the inverter
Check the power absorbed by the inverter
Check the batteries voltage through the BMS
Check the batteries current through the BMS
Set the '
P setpoint
' to 0
Set up the user requirements for harmonics and reactive power/ balancing
Check the line currents (Irms, THDI and waveforms)
Check the line voltage (Vrms, THDV and waveforms)
9.4 Testing (with battery)
Remarks:
(a)
Refer to Section 3.3 of the manual for more information on this topic.
(b)
Refer to Section 6 of the manual for more information on this topic.
—
NOTE: During the load test with the batteries keep the monitoring of the batteries parameters to avoid any value be out of
proper range of operation.
Project:
PQstorI
Issued by:
Commissioning report
Date:
Page 4 of 6