14.2.2.8
Restoring
Maintenance is very important to improve the availability of the protection system by
detecting failures before the protection is required to operate. There is however little
point in testing healthy equipment and then putting it back into service with an open
terminal, with a removed fuse or open miniature circuit breaker with an open
connection, wrong setting, and so on.
Thus a list should be prepared of all items disturbed during test so that all can be put
back into service quickly and without overlooking something. It should be put back
into service item by item and signed by the responsible engineer.
1MRK502053-UEN B
Section 14
Commissioning and maintenance of the fault clearing system
Generator protection REG670 2.0 IEC
245
Commissioning manual
Summary of Contents for REG670 2.0 IEC
Page 1: ...Relion 670 series Generator protection REG670 2 0 IEC Commissioning manual ...
Page 2: ......
Page 16: ...10 ...
Page 30: ...24 ...
Page 58: ...52 ...
Page 62: ...56 ...
Page 76: ...70 ...
Page 90: ...84 ...
Page 94: ...88 ...
Page 108: ...102 ...
Page 246: ...240 ...
Page 252: ...246 ...
Page 267: ...261 ...