Maintenance is very important to improve the availability of the protection system
by detecting failures before the protection is required to operate. There is however
little point in testing healthy equipment and then putting it back into service with
an open terminal, with a removed fuse or open miniature circuit breaker with an
open connection, wrong setting, and so on.
Thus a list should be prepared of all items disturbed during test so that all can be
put back into service quickly and without overlooking something. It should be put
back into service item by item and signed by the responsible engineer.
1MRK 506 383-UEN A
Section 11
Commissioning and maintenance of the fault clearing system
Line distance protection REL650 2.2 IEC
181
Commissioning manual
Summary of Contents for REL650 series
Page 1: ...RELION 650 SERIES Line distance protection REL650 Version 2 2 Commissioning manual...
Page 2: ......
Page 24: ...18...
Page 28: ...22...
Page 38: ...32...
Page 54: ...48...
Page 58: ...52...
Page 178: ...172...
Page 182: ...176...
Page 188: ...182...
Page 196: ...190...
Page 206: ...200...
Page 207: ...201...