Mounting panel
•
Metallic frame for mounting the RTXP 18 or 24 test switch to the panel
An IED equipped with optical connections requires a minimum
depth of 180 mm. The allowed minimum bending radius has to be
checked from the optical cable manufacturer.
To rack mount the IED into a 19" equipment frame:
1.
Mount the mounting panel into the 19" rack.
2.
Loosen the four M5 fixing screws in the case to fit the case into the panel cut-
out.
3.
Mount the case to the panel cut-out.
4.
Install the optional metallic frame to mount the RTXP 18 or 24 test switch to
the panel.
A071312 V3 EN
Figure 19:
Mounting of the metallic frame for an RTXP 18 test switch
1MRS756375 K
Section 4
Mounting
615 series
33
Installation Manual
Summary of Contents for Relion 615 series
Page 1: ...Relion Protection and Control 615 series Installation Manual ...
Page 2: ......
Page 8: ......
Page 11: ...Section 9 Glossary 73 Table of contents 615 series 3 Installation Manual ...
Page 12: ...4 ...
Page 78: ...70 ...
Page 80: ...72 ...
Page 82: ...74 ...
Page 83: ...75 ...