tool configuration is changed, but no changes are done for the instantiation or deletion
of functions that represent a logical node.
When a changed configuration is written to the IED, the user is asked to update the
communication configuration.
1.
Select
Yes
in the
Update Communication
window to update the
communication configuration part in the IED.
2.
Select
No
in the
Update Communication
window to keep the communication
configuration part in the IED. Other parts of the configuration will be updated.
If no changes have been done in the communication
configuration part, click
No
in the
Update Communication
window.
IEC09000729-2-en.vsd
IEC09000729 V2 EN
Figure 85:
Updating the communication configuration in the IED with the
configuration made in PCM600
7.7
IET600 engineering
After the IED configurations are prepared in PCM600, IEC 61850 communication is
engineered in an IEC 61850 system configuration tool, where the substation section
part, horizontal GOOSE communication and connections between IEDs and event
reporting clients (SCADA, gateway) can be configured.
In PCM600 Ver. 2.4 or later the recommended IEC 61850 system configuration tool is
IET600, which is also included in the PCM600 Engineering Pro package. See IET600
documentation for more detailed description of the features.
7.7.1
Managing projects
•
Create a new project.
Section 7
1MRS756800 F
IEC 61850 communication engineering
112
630 series
Engineering Manual