Section 4
Starting up
4.1
Factory and site acceptance testing
GUID-38C2B5FA-9210-4D85-BA21-39CE98A1A84A v2
Testing the proper IED operation is carried out at different occasions, for example:
•
Acceptance testing
•
Commissioning testing
•
Maintenance testing
This manual describes the workflow and the steps to carry out the commissioning testing.
Factory acceptance testing (FAT) is typically done to verify that the IED and its corresponding
configuration meet the requirements of the utility or industry. This test is the most complex
and in depth, as it is done to familiarize the user with a new product or to verify a new
configuration. The complexity of this testing depends on several factors, such as:
•
New IED type
•
New configuration
•
Modified configuration
Site acceptance testing (SAT or commissioning testing) is typically done to verify that the
installed IED is correctly set and connected to the power system. SAT requires that the
acceptance testing has been performed and that the application configuration is verified.
Maintenance testing is a periodic verification that the IED is healthy and has correct settings,
depending on changes in the power system. There are also other types of maintenance
testing.
4.2
Commissioning checklist
GUID-93D14E4E-5DDE-4D37-84A6-2DF0656AB73D v3
Before starting up commissioning at site, check that the following items are available.
•
Single line diagram
•
Protection block diagram
•
Circuit diagram
•
Setting list and configuration
•
RJ-45 Ethernet cable (CAT 5)
•
Three-phase test kit or other test equipment depending on the complexity of the
configuration and functions to be tested.
•
PC with PCM600 installed along with the connectivity packages corresponding to the IEDs
to be tested.
•
Administration rights on the PC, to set up IP addresses
•
Product documentation (engineering manual, installation manual, commissioning manual,
operation manual, technical manual and communication protocol manual)
1MRK 502 067-UEN B