97
Distance protection
Chapter 11
Verifying settings by secondary
injection
Measurements/Monitoring/Voltage phasors
3.
Repeat steps
to
to find the operate values for the remaining test
points according to figures
and to
table 30
Note, that if the shaped load encroachment characteristic is not activated
OperationLdCh=Off
then the test points 4, 5, 6 and 7 can be replaced by
number 12.
4.
Repeat steps to to find the operate value for the phase to phase fault
in L1 — L2 according to figure and compare with
table 30
.
Note, that if the shaped load encroachment characteristic is not activated
OperationLdCh=Off
then the test points 4, 5 and 6 can be replaced by
number 12.
5.
Repeat steps to to find the operate value of a three phase fault ac-
cording to
figure
and compare the result with
6.
Continue to test another function or complete the test by setting the
test mode to off.
5.3
Power swing detection (RPSB, 78)
The aim of this instruction is to verify the settings of the PSD function and to verify that the PSD
covers all impedance zones that should be blocked by the PSD.
Prepare the IED for verification of settings as outlined in
section 2
in this chapter.
Before starting this process, all impedance measuring zones shall be set and in operation. The
inner zone of the PSD must cover all zones to be blocked by the PSD by at least 10% margin.
See
figure 31
below.
Summary of Contents for RELION REL670
Page 8: ...Contents ...
Page 72: ...64 About this chapter Chapter 9 Establishing connection and verifying the LON communication ...
Page 174: ...166 Remote communication Chapter 11 Verifying settings by secondary injection ...
Page 190: ...182 Maintenance Chapter 13 Fault tracing and repair ...
Page 198: ...190 Glossary Chapter 14 Glossary ...