10.8.5
Delta supervision of real input DELSPVC
GUID-86ADAAC5-B6D3-46FE-A090-81F7C90A31A7 v1
Prepare the IED for verification of settings outlined in Section
.
10.8.5.1
Verifying the signals and settings
GUID-8337C76B-A361-426E-B936-763105D85588 v1
Make sure that the function is connected to any of the available real derived
outputs, for example the P output signal of the CMMXU function.
1.
Set the following parameters:
•
Operation
= ON
•
MinStVal
= 10
•
DelSt>
= 100
•
DeltaT
= 7
•
tHold
= 100
2.
Set a constant voltage input of UL1 = 63.5 V at 0° and UL2 = 63.5 V at 180°
secondary and a current signal at IL1 = 1A at 0° and IL2 = 1A at 180°.
3.
Ensure that the P output of CMMXU function has exceeded 10 MW and
remains stable.
4.
Change the current signal at IL1= 2A at 0° and IL2= 2A at 180°. Both
START and STARTRISE signals should be active for 100 ms.
5.
Change the current signal at IL1= 1A at 0° and IL2= 1A at 180°. Both
START and STARTLOW signals should be active for 100 ms.
10.8.5.2
Completing the test
GUID-2FE5E5F0-0E6C-499E-93D2-471C183B89BF v2
Continue to test another function or end the test by changing the
TestMode
setting
to
Off
. Restore connections and settings to their original values, if they were
changed for testing purposes.
10.9
Control
SEMOD53560-1 v1
10.9.1
Synchrocheck, energizing check, and synchronizing
SESRSYN
M2377-3 v12
This section contains instructions on how to test the synchrocheck, energizing
check, and synchronizing function SESRSYN.
Prepare the IED for verification of settings outlined in Section
.
1MRK 506 377-UEN C
Section 10
Testing functionality by secondary injection
Railway application RER670 2.2 IEC
129
Commissioning manual
Summary of Contents for RELION RER670
Page 1: ...RELION 670 SERIES Railway application RER670 Version 2 2 IEC Commissioning manual...
Page 2: ......
Page 26: ...20...
Page 54: ...48...
Page 58: ...52...
Page 62: ...56...
Page 80: ...74...
Page 188: ...182...
Page 194: ...188...
Page 204: ...198...
Page 214: ...208...
Page 215: ...209...