13. Using the local HMI, set Transformer 2 to Master of the parallel group and
T1 to Follower (in that order) and repeat steps
. Undertake this same
test by setting each Transformer in turn to Master.
14. Note that voltage regulation will be mutually blocked if no transformer is set
to Master in the parallel group. To confirm this function, set T1 as Master in
the parallel group and allow automatic voltage regulation to occur in a way
that the measured bus voltage is stable around
USet
. Without allocating a new
Master, set T1 to Follower and note the Automatic block state on the local
HMI for all parallel transformers.
15. Restore T1 to Master of the parallel transformer group and ensure that control
mode for each transformer is Automatic,
OperationPAR
is set to
MF
and
settings for
USet
are restored to normal in the service values.
14.1.1.6
Completing the test
Continue to test another function or end the test by changing the
Test mode
setting
to
Off
. Restore connections and settings to their original values, if they were
changed for testing purposes.
Section 14
1MRK 504 088-UEN C
Primary injection testing
212
Installation and commissioning manual
Summary of Contents for RELION RET670
Page 1: ...Relion 670 series Transformer protection RET670 Installation and commissioning manual...
Page 2: ......
Page 16: ...10...
Page 24: ...18...
Page 26: ...20...
Page 28: ...22...
Page 82: ...76...
Page 88: ...82...
Page 94: ...88...
Page 104: ...98...
Page 110: ...104...
Page 210: ...204...
Page 230: ...224...
Page 239: ...233...