Figure 67:
General test connection for a 1½ breaker diameter with one-phase
voltage connected to the line side
13.11.1.1
Testing the synchronizing function
This section is applicable only if the synchronizing function is included.
The voltage inputs used are:
UP3LN1
UL1, UL2 or UL3 line 1 voltage inputs on the IED
UP3BB1
Bus1 voltage input on the IED
Testing the frequency difference
The frequency difference is in the example set at 0.20 Hz on the local HMI, and the
test should verify that operation is achieved when the
FreqDiffMax
frequency
difference is lower than 0.20 Hz. The test procedure below will depend on the
settings used.
1.
Apply voltages
Section 13
1MRK 504 088-UEN C
Verifying settings by secondary injection
176
Installation and commissioning manual
Summary of Contents for RELION RET670
Page 1: ...Relion 670 series Transformer protection RET670 Installation and commissioning manual...
Page 2: ......
Page 16: ...10...
Page 24: ...18...
Page 26: ...20...
Page 28: ...22...
Page 82: ...76...
Page 88: ...82...
Page 94: ...88...
Page 104: ...98...
Page 110: ...104...
Page 210: ...204...
Page 230: ...224...
Page 239: ...233...