Section 7
Testing functionality
7.1
Testing disturbance report
7.1.1
Introduction
M17101-2 v5
The following sub-functions are included in the disturbance report function:
•
Disturbance recorder
•
Event list
•
Event recorder
•
Trip value recorder
•
Indications
If the disturbance report is set on, then its sub-functions are also set up and so it is not
possible to only switch these sub-functions off. The disturbance report function is switched
off (parameter
Operation = Off) in PCM600 or the local HMI under Main menu/Settings/IED
Settings/Monitoring/Disturbance report/DRPRDRE:1.
7.1.2
Disturbance report settings
M11746-2 v5
When the IED is in test mode, the disturbance report can be made active or inactive. If the
disturbance recorder is turned on during test mode, recordings will be made. When test mode
is switched off all recordings made during the test session are cleared.
Setting
OpModeTest for the control of the disturbance recorder during test mode are located
on the local HMI under Main menu/Settings/IED Settings/Monitoring/Disturbance report/
DRPRDRE:1.
7.2
Identifying the function to test in the technical
reference manual
M11748-2 v3
Use the technical manual to identify function blocks, logic diagrams, input and output signals,
setting parameters and technical data.
7.3
Testing current protection functions
7.3.1
Instantaneous phase overcurrent protection 3-phase output
PHPIOC
M11754-3 v7.1.1
Prepare the IED for verification of settings as outlined in section
.
Values of the logical signals for PHPIOC are available on the local HMI under Main menu/
Tests/Function status/Current/PHPIOC(50,I>>)/PHPIOC:1. The Signal Monitoring in PCM600
shows the same signals that are available on the local HMI.
To verify the settings the following fault type should be tested:
•
Phase-to-earth fault
1MRK 505 293-UEN B
Section 7
Testing functionality
Breaker protection REQ650
43
Commissioning manual
© Copyright 2013 ABB. All rights reserved
Summary of Contents for REQ650 1.3 IEC
Page 1: ...Relion 650 SERIES Breaker protection REQ650 Version 1 3 IEC Commissioning manual ...
Page 2: ......
Page 12: ...6 ...
Page 20: ...14 ...
Page 28: ...22 ...
Page 40: ...34 ...
Page 42: ...36 ...
Page 116: ...110 ...
Page 123: ...117 ...