Positioning anchor plates E1.2
The following diagram shows the distance for positioning the first anchor plate for E1.2 circuit-breakers
according to the peak current:
100/
3.94
150/
5.91
200/
7.87
250/
9.84
300/
11.81
350/
13.78
400/
15.75
450/
17.72
500/
19.69
40
60
80
100
120
140
160
E1.2
L
L
L
L
L
L
Figure 92
(1): distance of the first anchor plate from the circuit-breaker terminals
(2): peak current
Positioning anchor plates E2.2-
E4.2-E6.2
The following diagram shows the distance for positioning the first anchor plate for E2.2-E4.2-E6.2 circuit-
breakers according to the peak current:
100/
3.94
150/
5.91
200/
7.87
250/
9.84
300/
11.81
350/
13.78
400/
15.75
450/
17.72
500/
19.69
40
60
80
100
120
140
160
180
200
220
240
260
280
300
E2.2
E4.2
E6.2
L
[m
m
]
(1)
Ipk [kA]
(2)
Figure 93
L
L
(1): distance of the first anchor plate from the circuit-breaker terminals
(2): peak current
Summary of Contents for SACE Emax E1.2
Page 2: ...ABB SACE Emax 2 2 2017 ABB 1SDH001330R0002 ECN000058721 Rev A ...
Page 8: ...VI 2017 ABB SACE Emax 2 1SDH001330R0002 ECN000058721 Rev A ...
Page 9: ...ABB SACE Emax 2 3 2017 ABB 1SDH001330R0002 ECN000058721 Rev A ...
Page 310: ...ABB SACE Emax 2 304 2017 ABB 1SDH001330R0002 ECN000058721 Rev A Service 1 Power Care ...