1YSA160003-EN - Rev. 5
9 / 19
D.4.
Installation
D.4.1.
General
Correct installation is very important. The manufacturer’s instructions must be
carefully studied and followed. It is good practice to use gloves for handling the pieces
during installation.
D.4.2.
Installation and Service Conditions
The following standards must be taken into particular consideration during installation and service:
-
IEC 60694.
-
IEC 61936: Electrical Installation.
-
ANSI C37 63: Automatic Sectionalizer.
-
All accident prevention regulations in relative countries.
The AutoLink is compatible with the Fuses bases model ICX from ABB, Type XS from SYC, Type C from AB Chance and Type
L from Cooper.
For special installation requirements or other operating conditions, please contact ABB.
D.4.3.
AutoLink setup
The following setting procedure for the actuating current, count parameters and mechanical arm actuator must be performed
according to the User Manual document for the AutoLink Electronic Sectionalizer and is explained bellow.
D.4.3.1.
Component parts of Each AutoLink
Figure 6.