Assembly Instructions / TPL79-C
4 Installing the turbocharger / 4.1 Completion work, if required
© Copyright 2020 ABB. All rights reserved.
HZTL455311P0016_EN
Rev.A
July 2020
Step 10:
u
Now tighten all TE and CE foot screws with the tightening torque in sequence (1, 2, 3, 4, 5,
6, 7, 8).
Table: Tightening torque sequence
Gas outlet branch position
TPL79-C
NB000 (045 / 315)
1, 2, 3, 4, 5, 6, 7, 8
NB090
1, 2, 3, 6, 5, 8, 7
NB270
2, 1, 4, 5, 6, 7, 8
Table 13
Table: Tightening torque
Product
Thread size [mm]
Tightening torque [Nm]
TPL79-C
M 36
3300
Table 14
--------------------------------------------------------------------------------------------------
4.1
Completion work, if required
u
Attach all gas, air, water and oil pipes in accordance with the enginebuilder's instructions.
u
Fit insulation components.
u
Fit speed sensor and plug in cable connector.
Page
16
/
21