9 TRIO 20.0/27.6-TL-OUTD-US-480 | Programming for HECO compliance
From the
Configuration
drop-down menu, click on
Set-up area access
, as shown in Figure 13 below.
The following menu will appear, as shown in Figure 14 below.
Fill in all fields, and finish by inserting the PASSWORD obtained from ABB solar inverter post-sales technical support and then
clicking OK to confirm. New features will be available in the software. Press the REFRESH button and click on any inverter icon in
the list, and new TABs will then appear, as shown in Figure 15 below. These new tabs are available for all inverters listed and are to
be used to change the iinverter parameters as discussed in section 3 - Parameter setting via software tool Aurora Manager Lite on
page 3 of this instruction.
Figure 13 - Access the Setup area access
Figure 14 - Setup menu
Figure 15 - Software features available