Installation and commissioning guide
1ZSC000562-AAK EN, REV. 2, 2019-07-03
4.5 Installation of the top flange, yoke-mounting
Prerequisite
This procedure can be started after the active part with tap-changer has been installed in the transformer tank.
Procedure
1.
Lower the active part into the transformer tank.
G006837
2.
Put the transformer-tank cover on the transformer tank.
3.
Install the O-ring (10).
NOTE!
This O-ring was removed from the
tap-changer in
Installation on the yoke ,
page
G004309
4.
Install the gasket in the groove (3) in the
transformer cover.
NOTE!
The gasket is not included in the
tap-changer delivery.
G004310
Summary of Contents for VUBB
Page 14: ...14 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Page 28: ...28 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Page 52: ...52 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Page 60: ...60 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Page 68: ...68 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Page 72: ...72 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Page 74: ...74 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Page 76: ...76 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...