Installation and commissioning guide
1ZSC000562-AAK EN, REV. 2, 2019-07-03
37
14.
Tighten the two outer hex screws (2).
G004380
Torque
10 Nm
15.
Tighten the four hex screws (2).
G004382
Torque
10 Nm
16.
Make sure that the axial play is less than 2 mm.
If the axial play is more than 2 mm:
1.
Loosen the hex screws (2).
2.
Move the coupling halves outwards (9).
3.
Tighten the hex screws (2).
G004387
Torque
10 Nm
Summary of Contents for VUBB
Page 14: ...14 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Page 28: ...28 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Page 52: ...52 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Page 60: ...60 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Page 68: ...68 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Page 72: ...72 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Page 74: ...74 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Page 76: ...76 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...