Installation and commissioning guide
1ZSC000562-AAK EN, REV. 2, 2019-07-03
6.3 Synchronization of the motor-drive
6.3.1 Synchronization of BUL2
Procedure
1.
Open the door (1).
G004434
2.
Open the inner panel (2).
G006506
3.
Inspect the brake assembly and make sure that
the motor-drive mechanism is in the correct
position.
NOTE!
The brake assembly is at position (3).
NOTE!
The correct position is when the roller
is centered in the notch (4).
G004433
Summary of Contents for VUBB
Page 14: ...14 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Page 28: ...28 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Page 52: ...52 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Page 60: ...60 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Page 68: ...68 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Page 72: ...72 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Page 74: ...74 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Page 76: ...76 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...