4.
Operate the motor drive mechanism to the
position (7) in the middle of the range.
G004468
5.
Turn the control selector switch S1 to position
local
.
G004510
6.
Turn the control switch S2 to operate the tap-changer in the raise direction.
NOTE!
If the phase sequence is incorrect (from the three-phase electrical supply), then the
motor-drive mechanism will move in the lower direction. The motor-drive mechanism will
oscillate around its service position until the control selector switch is turned to 0.
7.
If the phase sequence is incorrect, reverse two of the motor-supply cables to get the correct
sequence.
DANGER!
Risk of electrocution!
8.
Turn the control switch S2 to operate the tap-changer.
Summary of Contents for VUBB
Page 14: ...14 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Page 28: ...28 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Page 52: ...52 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Page 60: ...60 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Page 68: ...68 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Page 72: ...72 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Page 74: ...74 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Page 76: ...76 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...