- Instruction Manual for ESS R050100-
12
3.3.1 Battery cabinet installation guide
Use professional handling equipment to move the cabinet to the installation site. The
equipment is placed on the back of the wall, and space for heat dissipation and safety is reserved.
The ground is kept flat, and the cabinet is connected to the wall by mounting parts for reliable
fixing.
Equipment handling method Battery cabinet
(1)
Transport the cabinet to the installation location. The floor of the cabinet installation must meet
the load-bearing capacity of 1200KG/m2; measure the size of the back-fixing parts using an
M8 drill bit, drill two holes with a depth of about 60mm on the wall, and knock in the
expansion bolts;
(2)
Remove the back-fixing parts: use a screwdriver to unscrew the 2 fixing screws on the
mounting bracket, and take off the fixing parts;
(3)
Pass the fixing parts through the expansion bolts, and fix them firmly with elastic flat washers
and nuts. The torque of the wrench is ≥4NM;
(4)
Place the cabinet close to the fixed wall, and use the removed screws to fix the cabinet and the
fixing parts firmly according to the way when the fixing parts are removed;
(5)
Adjust the equipment foot to make the cabinet steadily placed on the ground;