Recommended Equipment
Aclara recommends installers have the following equipment available during
installation. A more detailed list for specific installations evironments is provided
in Appendix A.
•
Cable ties
•
Staple gun
•
9/16" rounded crown staples
•
Fine point permanent marker
•
#6 x 1"Plastic anchors for screws
•
8" x 1-3/4" exterior screws
•
Hammer
•
Flashlight
•
Diagonal cutters
•
Wire stripper
•
Drill bits
•
#6 x 1-5/8" drywall screws
•
Cordless drill
•
Screwdrivers and screwdriver bits
•
Silicone gel filled electrical insulating IDCs
(Aclara #043-1913)
•
Connector appropriate crimping tool
•
Cellular phone (for relative signal strength)
•
Room Temperature Vulcanizing (RTV)
sealant
•
3 conductor, 22 AWG, single-strand, black
UV jacket cable
•
3 conductor, 22 AWG, single-strand, gray
UV jacket cable
•
Known operational MTU
•
Known operational meter equivalent to
meter at premise
•
Direct bury splice kit (Aclara #043-1912)
Summary of Contents for MTU
Page 2: ......
Page 4: ...ii M T U I n s t a l l a t i o n G u i d e l i n e s Table of Contents...
Page 6: ...iv M T U I n s t a l l a t i o n G u i d e l i n e s FCC IC Compliance...
Page 14: ...8 M T U I n s t a l l a t i o n G u i d e l i n e s Signal Propagation...
Page 28: ...22 M T U I n s t a l l a t i o n G u i d e l i n e s...
Page 30: ......