background image

MAN055 

– REV. 0   DATE: 11.01.2011      

 DRAFT BY:  U.T. 

PAG. 4 DI 9 

 

 
Acqua Brevetti 95 s.r.l. 

 

  

 

 

 

3.0 FILTER INSTALLATION 

3.1 GENERAL INSTALLATION RULES 

According to Italian Regulation the installation of the filter must be done by a qualified company that should provide a 

certificate  for  correct  installation.  The  installer  should  leave  a  technical  document  containing  clear  indications  about 

fittings, zone valves, sampling taps, drainage points and any other element pertaining assembly of the appliance. Such 

documents should be attached to the user’s manual and consigned to the

 customer.  

Install the filter observing all applicable local installation regulations, general guidelines and technical specifications. 

The semi-automatic cleaning filter PuliFIL protects hydraulic systems from foreign bodies. 

 

 

Attention!  

Check  for  the  right  connections  of  water  inlet  and  outlet.  The  entrance  and  exit  of  water  must  be 

concordant with the direction of the arrow printed on filter brass head. 

 

 

-

 

Before  installation,  please  observe  all  applicable  installation  regulations,  general  guidelines  and  technical 

specifications. 

-

 

Before  installation  clean  thoroughly  pipes  and  equipments  installed  before  the  filter  to  eliminate  any  foreign 

body. 

-

 

It is advisable to install shut-off valves immediately up-stream and down-stream the unity 

-

 

It is advisable to install a by pass valve to by-pass the filter during maintenance 

-

 

It is advisable to install sampling points up-stream and down-stream the filter to verify efficacy of filtering unit.  

-

 

The installation site must be protected against frost and must guarantee the protection of the unit from all types 

of chemicals, paints, heating oils, lees, solvent vapours, heat sources above 40°C and direct sunlight. 

-

 

Leave sufficient space for unscrew filter bowl. 

-

 

After installation verify for water leakage 

 

3.2 HYDRAULIC CHECKS AFTER THE INSTALLATION 

After opening water to filter unit please verify for water leakage: 

1. Verify that the installation allows maintenance 

2. Verify the presence of a by pass circuit to exclude the pump from main water supply line during servicing;  

3. Verify the sampling points upstream and downstream the filtering unit; 

4.  Verify  that  the  installation  is  compliant  with  local  installation  regulations,  general  guidelines  and  technical 

specifications. 

 
4.0 GENERAL INSTALLATION FLOW SHEET 

 

 

 
 
 
 

Legenda 

1. 

Cold water inlet; 

2. 

Water flow meter; 

3. 

Back flow prevention device; 

4. 

Zone valve; 

5. 

Sampling tap; 

6.

 By-pass 

valve; 

7. 

BravoFIL filter; 

8. 

Cold water outlet; 

9.

 Discharge.

 

Summary of Contents for BravoFIL Plus

Page 1: ...OPERATING MANUAL SEMI AUTOMATIC SELF CLEANING FILTER WITH PRESSURE REDUCER BravoFIL Plus Semi automatic self cleaning filter with pressure reducer BravoFIL Plus Fittings Code FT120 1 FT122 1 1 4 FT12...

Page 2: ...DI 9 Acqua Brevetti 95 s r l DIMENSIONS The dimensions are in mm Filter Code A B C D E F mm FT120 180 270 105 375 400 160 FT122 175 270 105 375 400 160 FT124 185 270 105 375 400 160 Document Revision...

Page 3: ...ch as sand silt rust oxides The filter is equipped with a pressure reducer that lets you adjust the pressure downstream thereof in a range of values ranging from 1 to 6 bar The maximum diameter of par...

Page 4: ...ments installed before the filter to eliminate any foreign body It is advisable to install shut off valves immediately up stream and down stream the unity It is advisable to install a by pass valve to...

Page 5: ...e high mechanical and corrosion resistance Pressure reducer In the back plate connection is housed the pressure reducer which is pre calibrated at the factory with an outlet pressure of 3 bar This val...

Page 6: ...t the turning of the green upper knob until the complete cleaning of the filtering cartridge is obtained Turn the filtering knob until the filtering position is reached with the discharge valve closed...

Page 7: ...1 8 Insert a curved pincer inside the discharge valve and rotate it clockwise to close the valve completely 1 9 Screw the brass nut insert the green plastic cover and put in the fork up as the initial...

Page 8: ...agraph 5 1 5 Placing the filter in phase Increase of the pressure downstream the pressure reducer in the presence of a boiler Water overheating increase of water volume Install an expansion tank The p...

Page 9: ...ents for performances safety and testing Acqua Brevetti 95 S r l operates with a Quality System certified according to Standard UNI EN ISO 9001 2000 with certificate N 50 100 7368 drafted by T V Itali...

Reviews: