14.  Test Run

Before  Commissioning

A test run must be performed after the entire system has been completely installed. Confirm the following points before 
performing the test:

a.  The indoor and outdoor units are properly installed.
b.  Piping and wiring are properly connected.
c.  Ensure that there are no obstacles near the inlet and outlet of the unit that might cause poor performance or product 

malfunction.

d.  The refrigeration system does not leak.
e.  The drainage system is unimpeded and draining to a safe location.
f.  The heating insulation is properly installed.
g.  The earth wires are properly connected.
h.  The length of the piping and the added refrigerant stow capacity have been recorded.
i.  The supply voltage is the correct voltage for the air conditioner.

 CAUTION

Failure to perform commissioning may result in unit damage, property damage or personal injury and may void warranty.

Commissioning Instructions

1.  Set the air conditioner to 

COOL

 mode.

2.  For the Indoor Unit

a.  Ensure the wall control and its buttons work properly.
b.  Check to see if the room temperature is being registered correctly.     
c.  Ensure the indicators on the wall control and the display panel on the indoor unit work properly.
d.   Check the airflow supplied matches the design conditions specified.

3.   Outdoor Unit

a.  Check to see if the refrigeration system is leaking.
b.  Make sure there is no vibration or abnormal noise during operation.
c.  Ensure the wind, noise, and water generated by the unit do not disturb neighbors or pose a safety hazard.
d.  Check the refrigeration pressures to ensure they operating correctly. 
e.  Check the voltage and current drawn from the unit is correct. 
f.  Ensure anti vibration rubbers have been fitted under the outdoor unit feet.

Drainage Test

1.  Ensure the drainpipe flows smoothly. Remove the test cover. Add 2,000ml of water to the tank through the attached 

tube.

2.  Turn on the main power switch and run the air conditioner in 

COOL

 mode.

3.  Listen to the sound of the drain pump to see if it makes any unusual noises.
4.  Check to see that the water is discharged. It may take up to one minute before the unit begins to drain depending on 

the drainpipe.

5.  Make sure that there are no leaks in any of the piping.
6.  Stop the air conditioner. Turn off the main power switch and reinstall the test cover.

NOTE

If the unit malfunctions or does not operate according to your expectations, please refer to the Troubleshooting section of 
the Owner’s Manual before calling customer service.

Summary of Contents for BRE-026CS

Page 1: ...e installing or operating your air conditioning unit Make sure to save this manual for future reference Model Numbers BRE 026CS BRE 035CS BRE 050CS BRE 070CS CAUTION The system is charged with flammab...

Page 2: ...0 14 Test Run 21 MUST BE INSTALLED BY A LICENSED ELECTRICIAN DIY DIY DIY ALL ELECTRICAL WORK MUST BE PERFORMED BY A LICENSED ELECTRICIAN FOR COMPLIANCE WITH QUEENSLAND ELECTRICAL SAFETY REGULATIONS 20...

Page 3: ...All electrical wiring must be in accordance with current electrical authority regulations and all wiring connections to be as per electrical diagram provided with the unit 03 General Information The A...

Page 4: ...mance capacity that are among the best in the market the ActronAir air conditioning units provide the solution for the reduction of energy consumption CO2 emission high fuel dependency and high networ...

Page 5: ...e room size corresponds to the room area as specific for operation without continuously operating open flames for example an operating gas appliance and ignition sources for example an operating elect...

Page 6: ...quipment does not leak or contain moisture Take into consideration the correct amount of refrigerant charge specified for the system to ensure efficient unit operations When charging is complete recla...

Page 7: ...ded with the air conditioner must be purchased separately Name Quantity Illustration Tubing Fittings Soundproof Insulation Sheath 2 Seal Sponge 1 Wired Controller Wired Controller 1 Wired Controller S...

Page 8: ...te controller based on customer preferences and requirements and install in an appropriate place Refer to catalogues and technical literature for guidance on selecting a suitable remote controller 07...

Page 9: ...locations In areas with oil drilling or fracking In areas with caustic gases in the air such as near hot spring In enclosed spaces such as cabinets In areas with strong electromagnetic waves In areas...

Page 10: ...nt te ed d h ho oo ok k Air filter Electric control box Air filter Air Intake Condensate Drain 25mm OD Air Intake Air Intake Model Outline Dimensions Supply Air Return Air Mounting Width Height Total...

Page 11: ...ng screw bolt Pipe hanging and embedding screw bolt Original Concrete Bricks Use an embedding screw bolt crock and stick harness Roof beam Hanging screw bolts Blade shape insertion Slide insertion Han...

Page 12: ...uld be apart far enough to avoid air passage short cycling Canvas tie in Canvas tie in Air outlet Isolation booth Isolation booth checking orifice Air inlet Air dust filter Air return flange Ventilati...

Page 13: ...ide using the following steps 1 Take off ventilation panel and flange cut off the staples at the side rail 2 Stick the attached seal sponge as per the indicating place see below and then change the mo...

Page 14: ...nsure correct electrical tag out procedures are followed before commencing work Take rear ventilated as example Motor Maintainance 1 Remove the ventilated panel 2 Remove the blower housing 3 Remove th...

Page 15: ...o the unit s outlet pipe Sheath the mouth of the hose and clip it firmly with a pipe clasp 3 Ensure the drain pipe has flex by installing clear tube or similar to prevent drain breakage or cracking Dr...

Page 16: ...TE When connecting multiple drainpipes install the pipes as shown below 0 550mm 100mm 4 Using a 65 mm core drill drill a hole in the wall Make sure that the hole is drilled at a slight downward angle...

Page 17: ...lfunction If you discharge the water directly into a sewer make sure that the drain has a U or S pipe to catch odour that might otherwise come back into the house Drainage Test Check whether the drain...

Page 18: ...ed size to ensure minimal voltage drop at supply terminals No other equipment should be connected to the same sub circuit as the A C unit The unit s power information can be found on the rating sticke...

Page 19: ...N L POWER SUPPLY See Outdoor Unit MRC Installation Guide for suggested minimum N INDOOR UNIT N L2 Field wiring by Installer 1mm 2 CORE EARTH S S 14 0 20 0 44mm SHIELDED DATA CABLE WITH SHIELD WIRE CON...

Page 20: ...ALARM NO RELAY OUTPUT 24V AC DC 0 5A MAX BY INSTALLER WIRED CONTROLLER WC 02 4 CORE SHIELDED CABLE COMES WITH WC 02 CN34 CN10 CHOKE M INDOOR COIL TEMPERATURE SENSOR T2 BLACK ROOM TEMPERATURE SENSOR T1...

Page 21: ...mperature is being registered correctly c Ensure the indicators on the wall control and the display panel on the indoor unit work properly d Check the airflow supplied matches the design conditions sp...

Page 22: ...Installation and Commissioning Guide Bulkhead 2 Split System Doc No 9590 5011 Ver 1 211217 22 Notes Bulkhead Split System...

Page 23: ...Installation and Commissioning Guide Bulkhead 2 Split System Doc No 9590 5011 Ver 1 211217 23 Notes Bulkhead Split System...

Page 24: ...Engineering Pty Limited ActronAir is constantly seeking ways to improve the design of its products Therefore specifications are subject to change without notice Refrigerant Trading Authorisation No AU...

Reviews: